Prosalia and EDP hybridise solar PV/wind projects with batteries in Portugal, Spain

LinkedIn
Twitter
Reddit
Facebook
Email

IPP Prosalia has commissioned a 15MW/60MWh battery storage system at a solar PV plant in Portugal, while power group EDP has added one to a hybrid wind and solar project in Spain.

Prosalia adds batteries to Portuguese solar PV plant

Independent power producer (IPP) Prosalia has integrated a 15MW/60MWh battery energy storage system (BESS) into its 34.4MWp Albispark solar PV plant in Castelo Branco, Portugal.

It is the company’s first solar-plus-storage project, and Portugal country manager Pedro Pereira da Silva commented: “After years focused on expanding renewable generation, the challenge now is to provide the flexibility needed to integrate that energy into the grid efficiently and securely. Energy storage plays a key role in this transformation.”

Trina Storage, part of the PV giant Trinasolar, provided the BESS units for the 4-hour duration project. Prosalia claimed it as one of the largest BESS projects in Portugal, in its announcement last month (23 July).

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The project received funding under Portugal’s share of the EU-wide Recovery and Resilience Plan (PRR) funding, via a scheme that is supporting 43 projects totalling 500MW of energy storage capacity, with winners finalised in January 2025. The Portuguese government is following that up with another auction for financial support for storage this year, following the Iberian blackout in April 2025.

Prosalia plans to hybridise its other solar PV plants in Portugal with BESS, including its Santo Varão (Coimbra, 5.5MW) and Algeruz (Palmela, 8MW) projects.

EDP adds batteries to solar and wind project in Spain

Power firm and utility EDP has added a BESS unit to its Las Lomillas solar and wind project in Cuenca, Spain, on which it is now undergoing testing.

That makes it the first of its kind in the Iberian Peninsula, Portugal-headquartered EDP said in its release also at the end of last month (29 July).

The project has 50MW of grid export capacity with a total of 122MW of capacity across the wind, solar and BESS portions. The project comprises:

  • 33 wind turbines totalling 49.5MW, installed in 2005
  • A 36MW solar PV array, installed in 2025
  • A 36MW/72MWh BESS, installed recently

The technologies are coordinated by an energy management system (EMS) that makes operational decisions based on advanced algorithms and under the supervision of EDP’s energy management teams and control centre, the company said.

The project also benefits from Recovery and Resilience funding from the EU, totalling €6.2 million (US$7.14 million). That scheme was also finalised last year.

EDP said it now has nearly 1GW of hybridised capacity across Portugal and Spain, around 75:25 split between the two countries. There are a mix of solar, BESS, wind, hydropower and pumped hydro.

Activity in Spain’s grid-scale energy storage market has picked up recently, with large-scale projects financed or offtake-contracted by project owners Return, Ignitis and Grenergy in the past month alone.

However, Ignacio López Martín, chair of developer Capflex Energía, wrote a guest blog for us recently in which he said that many people misunderstand the BESS opportunity in Spain – read that here.

2 December 2026
Italy
Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.

Read Next

August 7, 2026
The German regulator BNetzA’s latest draft decision on grid fees from 4 August 2029 onwards still leaves uncertainty for energy storage project business cases.
August 7, 2026
The Spanish Ministry of Ecological Transition (MITECO) has awarded €360 million (US$415 million) to 1.14GW of solar PV co-located with battery energy storage system (BESS) projects.
August 6, 2026
Denmark-headquartered multinational energy company Ørsted has put its 250MW/500MWh Old 300 energy storage project in Needville, Texas, US into operation.
August 6, 2026
IPP Zelestra has agreed a long-term toll for a 99MW/297MWh BESS project in Germany with the trading arm of UK-based power group Centrica.
Premium
August 5, 2026
Elestor claims its hydrogen-iron flow battery delivers 75%+ round-trip efficiency, a 20-25 year lifespan, and 15€/kWh capex for long-duration storage.