UK investment manager Downing contracts Hyosung Heavy Industries for 50MW battery storage project

February 24, 2021
LinkedIn
Twitter
Reddit
Facebook
Email
Downing’s only battery project to date was a 3MW Tesla Powerpack industrial system installed at the stadium of London soccer club, Arsenal. Image: Pivot Power.

UK investment management group Downing LLP has announced its first utility-scale battery storage site in the country, a 50MW/53MWh project in Nursling, Southampton on England’s southern coast.

The group, which invests in diverse assets with a claimed focus on social and sustainable investing including the renewable energy sector, has selected its co-funding partner as well as having entered into agreements for the supply of the storage solution, the optimisation of the asset and the route to market and trading arrangements.

Grid connection work is already largely complete at the site, which is managed by UK-based construction company Arun Construction Services. It will work as the principal contractor through the installation of the asset, which is expected to connect to the grid and begin operation in August 2021.

The battery storage solution will be provided by South Korean supplier Hyosung Heavy Industries corporation in what will be its first transmission-connected battery project in the UK.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Downing’s Nursling project will be connected to National Grid’s transmission system directly, as well as the company targeting a private wire network and utility-scale electric vehicle charging super hub in the second phase of the project.

Following a tendering process, EDF has been selected to optimise the project, providing a route-to-market and acting as trading partner as part of a seven-year contract.

To read the full version of this story, visit Solar Power Portal.

Our publisher Solar Media is hosting the Energy Storage Summit 2021 in an exciting new format on 23-24 February and again on 2-3 March. See the website for more details.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

February 24, 2026
Panellists discussed M&A in large-scale BESS on the ‘M&A Market: How Attractive Is BESS Right Now?’ panel discussion at the Energy Storage Summit 2026.
February 24, 2026
How to enable bankability for large-scale BESS projects was the main topic of the opening panel discussion at the Energy Storage Summit 2026 which kicked off today (24 February).
February 24, 2026
The recent successes of the energy storage market in Europe bring new challenges alongside industry maturity, writes Vicente Abad.
February 23, 2026
Operational experience, credibility and optimisation performance are becoming key to BESS bankability, writes Jürgen Mayerhofer, CEO and co-founder of optimiser Enspired.
February 20, 2026
A flurry of BESS project news from big-name players in Western Europe in the run-up to the Energy Storage Summit next week, with Neoen, Statkraft, Zenobē and Infranode moving projects forward in Germany, Ireland, the UK and Denmark. Highlights include a 15-year toll between Drax and Zenobē, and multiple 4-hour duration systems.