UK investment manager Downing contracts Hyosung Heavy Industries for 50MW battery storage project

February 24, 2021
LinkedIn
Twitter
Reddit
Facebook
Email
Downing’s only battery project to date was a 3MW Tesla Powerpack industrial system installed at the stadium of London soccer club, Arsenal. Image: Pivot Power.

UK investment management group Downing LLP has announced its first utility-scale battery storage site in the country, a 50MW/53MWh project in Nursling, Southampton on England’s southern coast.

The group, which invests in diverse assets with a claimed focus on social and sustainable investing including the renewable energy sector, has selected its co-funding partner as well as having entered into agreements for the supply of the storage solution, the optimisation of the asset and the route to market and trading arrangements.

Grid connection work is already largely complete at the site, which is managed by UK-based construction company Arun Construction Services. It will work as the principal contractor through the installation of the asset, which is expected to connect to the grid and begin operation in August 2021.

The battery storage solution will be provided by South Korean supplier Hyosung Heavy Industries corporation in what will be its first transmission-connected battery project in the UK.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Downing’s Nursling project will be connected to National Grid’s transmission system directly, as well as the company targeting a private wire network and utility-scale electric vehicle charging super hub in the second phase of the project.

Following a tendering process, EDF has been selected to optimise the project, providing a route-to-market and acting as trading partner as part of a seven-year contract.

To read the full version of this story, visit Solar Power Portal.

Our publisher Solar Media is hosting the Energy Storage Summit 2021 in an exciting new format on 23-24 February and again on 2-3 March. See the website for more details.

Read Next

January 21, 2026
The UK market saw strong interest and activity in 2025 but now appears to be shifting from a development market to one focused on execution, writes Solar Media analyst Charlotte Gisbourne.
January 21, 2026
Another roundup of European grid-scale BESS project news, led by MORE and Zenobe putting Greece and UK projects into operation, and major project financings/construction starts by Acacia in France, Greenvolt in Hungary and Eco Stor in Germany.
January 20, 2026
While the UK grid-scale BESS market continues to be among the busiest in Europe, there are still huge questions and plenty work to be done in several key policy areas.
Premium
January 19, 2026
US-based iron-sodium battery manufacturer Inlyte Energy has successfully completed a factory acceptance test of its first field-ready battery at its facility near Derby, UK, witnessed by representatives from US utility Southern Company.
January 19, 2026
Virtual BESS tolling platform startup Terralayr has raised €192 million (US$223 million), primarily for its own build-own-operate BESS pipeline. CEO Philipp Man spoke to Energy-Storage.news about the funding round and growing its capacity virtualisation and tolling platform.