South Australia takes Tesla up on ‘100 days or free’ energy storage promise

LinkedIn
Twitter
Reddit
Facebook
Email
Tesla Powerpack utility batteries. Image: Tesla

An offer from Tesla CEO Elon Musk to complete a large-scale energy storage project in South Australia within 100 days or deliver it for free has been taken up by the region’s government.

Since suffering blackouts, especially the severe ones caused by weather events in September last year, South Australia’s precarious energy security has come into question and local government has been keen to find a quick and lasting solution. The South Australia administration sought self-reliance and to add energy capacity.

In March, Musk made headlines when he made a direct offer in a Twitter conversation with Australian tech entrepreneur Mike Cannon-Brookes for Tesla to have a 100MW lithium-ion battery system “installed and working within 100 days from contract signature” – or waive all charges. This followed similar claims made by Musk’s cousin, SolarCity’s former CEO Lyndon Rive in an interview with Australian media.

“That serious enough for you?” Musk said.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

This morning, South Australia premier Jay Weatherill announced that Tesla had indeed agreed to execute a 100MW / 129MWh energy storage project at a wind farm operated by French company Neoen after winning a competitive tender process. Weatherill added that the “100 days or free” condition is in place. That “contract signature” date Musk referred to as the starting gun for the 100 day countdown has been taken to mean the date grid interconnection agreements are signed.

The project will be located at Neoen’s Hornsdale Wind Farm, a facility that will have 315MW of generation capacity when completed, with construction well underway. The battery energy storage system will be used to keep South Australia’s electrical infrastructure reliable, charging from the wind farm and discharging to the grid at times of peak and high demand. It will also assist the smooth integration of variable wind energy into the network and to provide backup power in the event of outages.

Neoen also had to participate in the tender process, and was selected from 90 expressions of interest whittled down to a shortlist of five. The French company, Tesla and the local government will work closely together on the project. As part of that bid, the Tesla-Neoen consortium said it would be able to deliver the 129MWh plant by 1 December.

Jay Weatherill’s office said that South Australia was also expecting further investments into the region from Tesla-Neoen, to be announced in future. The premier’s statement on the news also expressed a wish that working with Neoen could foster links between France’s tech sector – of which French president Emmanuel Macron has spoken very highly – and South Australia’s economy.

In a corporate blog post, Tesla said it was “proud to be part of South Australia’s renewable energy future”.

“…we expect this project will provide a model for future deployments around the world that will help significantly accelerate the adoption of sustainable energy,” the company said.

“Battery storage is the future of our national energy market, and the eyes of the world will be following our leadership in this space,” South Australia premier Weatherill said.

“This historic agreement does more than bring a sustainable energy giant in Tesla to South Australia, it will also have some significant economic spin-offs.”

Meanwhile, Neoen deputy CEO Romain Desrousseaux said his company was “extremely proud” to be working on the project.

“At 100MW and 129MWh, the Hornsdale Power Reserve will become not only the largest renewable generator in the state but also home to the largest lithium ion battery in the world, with our company’s long-term, direct investment in South Australia growing to almost $1 billion since 2013,” Desrousseaux said.

“Together, the South Australian Government, Neoen and Tesla will demonstrate that renewables can provide dependable, distributable power that will turn a new page in Australia’s energy future.”

Hornsdale Wind Farm follows on the heels of a Tesla-executed large-scale dispatchable solar and energy storage plant in Hawaii. The company also has experience of executing battery projects to provide capacity in quick-time: it was one of those behind the expedited California energy storage projects put in place in less than six months to deal with the capacity shortfall caused by the Aliso Canyon natural gas leak.

Read Next

July 23, 2026
Spain has awarded €165 million to seven pumped hydro storage projects totalling around 2.1GW/21GWh, while Portugal has set a target of 1.4GW of new pumped hydro capacity by 2040.
July 23, 2026
Tesla’s energy storage deployments rebounded in the second quarter of this year, but factors, including a decline in ASPs, had a significant impact on the company’s energy division’s gross margins.
Sponsored
July 22, 2026
We caught up with Michael Koller, Solutions Director for Europe and the UK with Envision Energy, at this year’s Smarter E Europe trade show in Munich. 
July 22, 2026
With the Energy Storage Awards 2026 entry deadline less than two months away, we speak to four judges to hear what they are looking for from successful entrants.
July 21, 2026
South Australia battery storage developer Lunio Energy has energised its first grid-scale BESS at Strathalbyn and started trading in the NEM.