NEC to power up investment fund Gore Street’s 100MW Northern Ireland projects

January 10, 2020
LinkedIn
Twitter
Reddit
Facebook
Email
NEC’s project at Glassenbury, UK. Image: VLC Low Carbon / NEC.

Gore Street Energy Storage Fund has awarded NEC Energy Solutions both EPC and long-term O&M contracts for 100MW of storage in Northern Ireland.

NEC has committed to construct the two 50MW projects at a fixed price by a specified completion date, to provide for performance and availability warranties and to operate the projects for up to 15 years.

The combination of fixed prices, warranties backed by liquidated damages and guaranteed completion dates further de-risk the projects, Gore Street said, with the projects on track to be commissioned in Q1 2021. Gore Street is one of two London Stock Exchange-listed, dedicated energy storage funds, the other being Gresham House, which has been on a wave of asset deals in recent months.

They are expected to earn revenue through the DS3 flexibility market, Gore Street said, alongside the two 30MW projects in the Republic of Ireland that have secured six year contracts. Gore Street intends to participate under the DS3 Standard Contracts tender in October 2020 and proceed with testing throughout December and January.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The Northern Ireland projects are also set to earn revenue through the Irish Capacity Remuneration Mechanism and, after the end of DS3 services, wholesale trading.

To read the full version of this story, visit Solar Power Portal.

Read Next

April 23, 2026
Developer-operator Green Capital and EPC firm Electrum Holding have signed an agreement to build an 80MW/320MWh BESS in Poland, under a full ‘wrap’ model.
Premium
April 22, 2026
How should developers and investors think about long-term BESS revenues in light of eventual market saturation?
April 22, 2026
US battery storage developer Key Capture Energy could be up for sale as its owner considers options to “bring in a financial partner”, Energy-Storage.news has heard.
April 21, 2026
BESS platform Ingrid Capacity has received construction permits for two projects in Sweden’s SE4 electricity region which it said could start construction as early as this year.
April 21, 2026
New Zealand generator-retailer Genesis Energy has reached Final Investment Decision (FID) on the second stage of its Huntly battery energy storage system (BESS).