Developer PureSky extends deadline in 1.6GWh Texas BESS portfolio sale

LinkedIn
Twitter
Reddit
Facebook
Email

Developer PureSky Energy has extended its Non-Binding Offer (NBO) deadline for a 794MW/1,588MWh portfolio of battery energy storage system (BESS) projects in Texas, US, to Friday, 24 January.

PureSky is being represented by Fractal Advisory, part of the Texas-based company Fractal Energy Storage Consultants. Fractal CEO Judy McElroy announced the NBO due date deadline extension via an update emailed to contacts, including Energy-Storage.news.

Referred to as Project Rio Grande, the portfolio includes five late-stage standalone BESS projects, all of which are targeting a Notice to Proceed in late 2025. The projects are detailed in the table below.

Project NameCountyUtilitySizeExpected COD
FloresStarrLower Colorado River Authority (LCRA)200MW, 2-hourApril 2027
Gongora HillStarrLCRA200MW, 2-hourApril 2027
ChihuahuaHidalgoAmerican Electric Power Texas (AEP)200MW, 2-hourApril 2027  
MinnesotaHidalgoLCRA94MW, 2-hourApril 2027
RichardsonHidalgoAEP100MW, 2-hourApril 2027

Hidalgo and Starr Counties are located in the Electric Reliability Council of Texas (ERCOT) South load zone. Both counties sit along the US-Mexico border.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

All of the projects for sale are also located in Energy Community-designated areas and are therefore eligible for a 10% bonus on tax credit incentives. These are areas defined as having been historically dependent on fossil fuel industries, including coal, oil, and gas, to support the local economy and workforce, including coal mining and coal-fired power plants.

According to a US Department of Energy map, the five projects in the Rio Grande portfolio are in areas that meet both the required Fossil Fuel Employment (FFE) threshold and unemployment rate requirement to quality as Energy Communities as of June 2024

Fractal has specified that while PureSky is seeking a full sale structuring, the company is open to offers in which it retains a minority equity partnership or other types of partnership that buyers may offer.  The company is also open to the sale of individual projects or the entire five-project portfolio.

The timeline of the sale is split into three phases. Phase 1, lasting approximately 4-5 weeks, includes submitting an Expression of Interest, NDA execution, and the bidder introductions. Phase 2 will last 7-8 weeks, including due diligence, completing questions and answers surrounding the sale, and ending with the refined bid. The third phase is the signing or closing of the sale, including identifying the winning bidder, outlining exclusivity and agreement execution.

Hidalgo County is also home to the 200MW/400MWh Anemoi standalone BESS(Premium access article), developed by Plus Power and cleared for operation in June 2024, and Apex Clean Energy’s 100MW/200MWh Great Kiskadee Storage project.

Texas continues to be an active market for BESS projects, driven by ERCOT’s wholesale market’s unique structure, which enables merchant opportunities for storage developers. The state accounted for 25% of a total 3,431MW/9,188MWh US grid-scale battery storage deployments recorded in Q3 2024, according to market research firm Wood Mackenzie’s most recent US Energy Storage Monitor Report.

A trend in the ERCOT market, as discussed in a July 2024 conversation with Energy-Storage.news and Modo Energy(Premium access article), is that revenues are becoming concentrated into a fewer number of days. This leads to an increase in volatility, where prices are either incredibly high or incredibly low.

Buyers of projects like the ones being represented in Project Rio Grande also have to consider the possibility of doing more energy arbitrage on the market.

Fractal is also representing Concurrent in the Project Silver Steel process, a portfolio containing two 10MW standalone BESS projects also located in ERCOT’s South load zone. The projects have an estimated COD of Q2 2026. Non-Disclosure Agreements for the portfolio are due by 20 January. More details can be found here (PDF). Additional details on the Project Rio Grande portfolio can be found here (PDF).

In addition to its advisory and consulting divisions, Fractal Energy Storage Consultants has a software division, Fractal EMS, which supplies energy management system (EMS) platforms to customers including LG Electronics, with which it signed a deal to use the EMS in commercial and industrial (C&I) battery storage systems in 2022.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
15 September 2026
Berlin, Germany
Launching September 2026 in Berlin, Energy Storage Summit Germany is a new standalone event dedicated to Germany’s energy storage market. Bringing together investors, developers, policymakers, TSOs, manufacturers and optimisation specialists, the Summit explores the regulatory shifts, revenue models, financing strategies and technology innovations shaping large-scale deployment. With Germany targeting 80% renewables by 2030, it offers a focused platform to connect with the decision-makers driving the Energiewende and the future of utility-scale storage.
3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

September 14, 2026
Heron Power and NeoVolta have secured significant credit facilities, while Carina Energy has launched a FEOC compliance support practice to help developers navigate increasingly complex regulatory requirements.
September 14, 2026
Lava Blue commissions Australia’s first grid-connected sodium-sulfur BESS, while ZEBRE’s 360MWh Noblevale BESS clears EPBC review.
Premium
September 14, 2026
Eku Energy’s Elias Saba discusses why he believes the CIS has not fundamentally changed the company’s investment approach.
September 11, 2026
Premier Energies and RCT India have established a joint venture to develop a 12GWh BESS manufacturing facility in Telangana, India.
September 11, 2026
Greek renewables developer Metlen Energy & Metals has signed an agreement with utility Copec for the sale of the Tamarico II solar-plus-storage project in Chile’s Atacama region.