Just over 70% of the successful projects in the first window of the UK’s long-duration energy storage (LDES) scheme use lithium-ion BESS technology.

UK energy regulator Ofgem revealed its final decision for which of the 171 applicant projects will now proceed to the project assessment period yesterday (23 September).

Ofgem has determined that 77 projects met the criteria, some of which are scheduled for 2030 operations (Track 1) and some for 2033 operation (Track 2).

The scheme will provide a cap-and-floor revenue stabilising mechanism to successful projects, which you can read more about in our coverage of a webinar on the topic by consultancy Baringa, published on ESN Premium on Monday.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The 77 projects total 28.7GW of capacity and will need to be deployed as, at a minimum, 8-hour systems.

By GW capacity, lithium-ion battery energy storage systems (BESS) account for 70.4%, pumped hydro accounts for 16.0%, vanadium flow battery/zinc battery hybrid projects for 9.1%, pure vanadium flow battery projects for 3.1%, with a handful of liquid air energy storage (LAES) BESS hybrid and compressed air energy storage (CAES) making up the remainder.

See the full table from Ofgem below, and the full list of projects in its document here.

The 16 projects with both vanadium flow battery and zinc battery as their chosen technology totalling 2.6GW of power are all from developer Frontier Power, which is aiming to use the technology from Invinity Energy Systems and Eos Energy Enterprises respectively.

BESS developer Field also had five BESS projects totalling 1.6GW progress, while Fidra saw its Thorpe Marsh project progress, though it only put forward part of its total capacity. Amongst the handful of successful pumped hydro projects was utility and power firm SSE’s Coire Glas project in Scotland.

The emergence of lithium-ion BESS as a real contender for LDES is relatively recent. OEM Envision Energy recently wrote a guest blog for us about how price falls have made it cost-competitive for 10-hour applications, and the global LDES pipeline now reflects this according to research firm Sightline Climate.

Mark Horley, Senior Policy Manager at Ofgem, will deliver the opening keynote on the LDES Cap & Floor Scheme at the Battery Asset Management Summit UK & Ireland, 14–15 October 2025 in London. Book your pass to hear directly from Ofgem on what comes next and how the scheme will provide long-term stability for UK battery storage assets.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

August 14, 2026
US ‘multi-day’ energy storage startup Noon Energy has made an agreement with renewables platform Sabanci Renewables, to deploy 1GW of Noon’s technology for AI infrastructure in the US.
August 13, 2026
NextEnergy UK has acquired a 107MW/151MWh portfolio of standalone battery energy storage system (BESS) projects in the UK.
August 13, 2026
Denmark-headquartered investor Copenhagen Infrastructure Partners (CIP) has brought its 500MW, 2-hour duration Coalburn 1 battery energy storage system (BESS) into commercial operation.
Premium
August 11, 2026
What led Field to submitting, and winning, 16- to 18-hour BESS projects in the UK’s long-duration energy storage (LDES) cap-and-floor scheme, and what are the next steps? We hear from the firm’s technical director.
August 10, 2026
In this news roundup, ACCURE, Hydrostor, Shoals and TerraFlow, and Qnetic claim significant advances in and for energy storage technology.