Leeward closes US$260 million financing for 352MWh solar-plus-storage project in California

LinkedIn
Twitter
Reddit
Facebook
Email

Wells Fargo, MUFG and Silicon Valley Bank have completed US$260 million of construction financing for Leeward Renewable Energy’s Chaparral Springs solar-plus-storage project in California.

The developer announced the securing of financing and tax equity commitments for Chaparral Springs yesterday (10 January). The project in Kern County, California, will combine 174MW of solar PV and a four-hour 88MW/352MWh battery energy storage system (BESS) once operational in September 2023.

The debt portion was issued under the Loan Market Authority’s Green Loan Principles. JP Morgan has provided US$29 million in tax equity investment and has committed to investing another US$114 million at commissioning.

Chaparral Springs will provide its energy under previously-announced 15-year power purchase agreement to Community Choice Aggregation (CCA) groups Peninsula Clean Energy and Valley Clean Energy. Energy-Storage.news reported on both agreements at the time. CCAs are not-for-profit, community-owned electricity providers.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Leeward said the financing announced yesterday is an extension of its previously-announced financing for its Rabbitbrush solar-plus-storage project, also in Kern County.

Chris Loehr, senior vice president of finance said: “This milestone follows the successful development and operation of our Rabbitbrush Solar project, which is adjacent to Chaparral Springs, and further demonstrates our commitment to excellence and ability to deliver on our pipeline of contracted projects. We value the continued support from our financial partners as we continue to drive our sustainability mission in all we do.”

California has an ambitious target to be completely carbon neutral by 2045. As it adds more renewables to achieve this goal, an imbalance between plentiful solar generation in the day and peak demand well into the evening has emerged, the so-called ‘Duck Curve’.

Battery storage projects are being brought online to mitigate this and the state now has around 4.5GW online as per grid operator CAISO’s most recent figures for 1 December, 2022. Like Chaparral, most new large-scale projects are four-hour systems in order to qualify for selling energy to utilities under Resource Adequacy, CAISO’s framework for ensuring there is enough supply to meet demand.

CAISO recently adopted market reforms that will make it easier for battery storage assets to play into energy markets by accounting for state of charge, as reported by Energy-Storage.news.

See all Energy-Storage.news coverage of the CAISO California market here.

Energy-Storage.news’ publisher Solar Media will host the 5th Energy Storage Summit USA, 28-29 March 2023 in Austin, Texas. Featuring a packed programme of panels, presentations and fireside chats from industry leaders focusing on accelerating the market for energy storage across the country. For more information, go to the website.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

October 1, 2026
Orix Corporation has begun construction of its first battery storage projects to be supported by external investment.
September 30, 2026
Three US utilities, Ameren Missouri, DTE Energy in Michigan, and Black Hills Energy in Colorado have recently submitted IRPs with highlighted BESS project additions.
September 30, 2026
IPP Northland Power has announced that its 80MW/160MWh Jurassic energy storage project in Cypress County, Alberta, CA, has achieved commercial operations.
September 30, 2026
Spain’s recent proposal for data centres could be the catalyst the country’s energy storage market has been waiting for, argues Ignacio López Martín from developer Capflex Energía.
Premium
September 29, 2026
Energy-Storage.news Premium speaks with Claire Lang-Ree, clean energy advocate at the Natural Resources Defense Council (NRDC), about PJM’s proposed capacity market reforms.