Fire at 20MW UK battery storage plant in Liverpool

By Andy Colthorpe
September 16, 2020
LinkedIn
Twitter
Reddit
Facebook
Email
Carnegie Road BESS in Liverpool, UK, as it looked when completed in early 2019. Image: Ørsted.

There has been a fire at the Carnegie Road 20MW battery energy storage system (BESS) project in Liverpool, England, project owner Ørsted has confirmed.

Merseyside Fire & Rescue Service, local first-responders, said that crews were alerted shortly before 1am on 15 September and arrived to find a “large grid battery system container well alight”.

The fire service said that it had used main jets and ground monitors in tackling the fire, asking residents nearby to keep their windows and doors closed due to smoke from the incident.

The blaze went on for several hours, with an update from the service at 7:30am noting that although operations at the site had been scaled down, firefighting was ongoing, with two ground monitor units and a main water jet still in use. A further update at 11:45am said one fire engine was still at the scene, with firefighting still continuing, although by that stage only one hand-held pump was in use.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The Carnegie Road project was Danish power company Ørsted’s first standalone grid-connected battery project, built using storage system equipment supplied by the now-defunct Energy Solutions division of NEC Corporation, housed in three containers. The project’s completion was announced at the beginning of 2019.

Ørsted sent a statement to Energy-Storage.news in response to a request for confirmation of the story and for further details:

“We can confirm there has been a fire at our Carnegie Road battery storage facility in Liverpool. This facility does not have permanent members of staff and no-one was on-site at the time of the fire,” the spokesperson said.

“We would like to thank the firefighters at Merseyside Fire and Rescue for their rapid response and professionalism in getting the fire under control. It is too early to speculate about the cause of the fire but as soon as we can get on-site we will be conducting an urgent review to understand what has happened.”

Merseyside Fire & Rescue Service also said that “an investigation will be carried out”.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

Premium
March 4, 2026
We caught up with Danske Commodities’ principal originator Rimshah Javed at the Energy Storage Summit 2026, to discuss trends in BESS offtake, optimisation, FCAs in Germany and the Danish market. The latter has taken off in the past year.
March 4, 2026
The Australian Capital Territory (ACT) has completed its first network of community batteries with the commissioning of a 450kWh system in Dickson.
March 3, 2026
3.6GWh of solar-plus-storage developments have progressed in Australia this week, with Edify Energy partnering with DT Infrastructure and Flow Power acquiring a 60MW project.
March 3, 2026
A second-round auction in the UK for grid stability services, including inertia, concluded without any wins for grid-forming battery energy storage system (BESS) projects.
March 3, 2026
Allianz GI, Luxcara and Return have acquired BESS projects and portfolios in Germany, Finland and Spain; Low Carbon, OX2, Cero Generation and Revera have taken FIDs on projects in Poland, Finland and the UK; and NHOA Energy has received a 600MWh order in Italy. All in all, the projects total at least 3.7GWh of capacity.