EDF Renewables brings online 620MWdc multi-stage PV project with 200MWh BESS in California

August 18, 2022
LinkedIn
Twitter
Reddit
Facebook
Email

EDF Renewables North America has fully commissioned Palen Solar, a multi-stage solar PV project on public lands in California administered by the US Bureau of Land Management (BLM).

The clean energy independent power producer (IPP) subsidiary of French energy multinational EDF said yesterday that the project’s 457MWac/620MWdc of ground mounted PV with horizontal single axis trackers and its 50MW/200MWh battery energy storage system (BESS) are now all fully up and running.

This follows an update from the Department of the Interior – of which BLM is an office – earlier this month reported by our sister site PV Tech to that effect, with EDF’s release yesterday adding a few project details.

Palen Solar includes four separate phases, the first of which went online in December 2020. The battery storage system was the final piece to be commissioned. They are as follows:

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Maverick 1: 173MWdc/125 MWac

Maverick 4: 137MWdc/100 MWac

Maverick 6: 131MWdc/100 MWac with 50MW/200MWh battery storage

Maverick 7: 179MWdc/132 MWac

The power plants are all in California’s Riverside County, and received approval from the BLM in 2018, on unincorporated land designated suitable for renewable energy development.

EDF signed a power purchase agreement (PPA) with fellow energy major Shell for a 100MW tranche of the project, also in 2018.

“The renewable energy industry has experienced significant volatility over the past years battling both unprecedented pandemic and supply chain constraints. We are excited to now have all four projects operating at full capacity and to contribute to California’s climate goal to reduce greenhouse gas emissions to 40% below 1990 levels by 2030,” EDF Renewables North America’s senior VP for implementation and project management Benoit Rigal said.

Operations and maintenance (O&M) of the plant will be carried out by EDF’s own asset optimisation group, including maximising power production through NERC compliance support, remote monitoring, and balance-of-plant management.   

Yesterday, Energy-Storage.news reported that another battery project on BLM-managed land in Riverside County has gone online. A 230MW BESS adjacent to an existing solar power plant has achieved the start of commercial operations, the Department of the Interior said. The project, Desert Sunlight, was developed by NextEra Resources, which also owns the solar farm of the same name next door.

It is part of a concerted effort for BLM to open up otherwise unused lands or brownfield sites to clean energy developments. PV Tech has reported on several other such development projects that have been granted approval, including a 250MW solar-plus-storage project in Arizona by Revolve Renewable Power and Oberon Solar, a 500MW solar project with 500MW of battery storage from developer Intersect Power, also in Riverside County.  

24 March 2026
Dallas, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2026!
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

March 10, 2026
Octopus Australia has broken ground on the 486MWh Blind Creek Solar Farm and Battery site in New South Wales (NSW).
March 10, 2026
The NSW Independent Planning Commission has approved Edify Energy’s 400MWh Burroway solar-plus-storage project in Australia.
March 9, 2026
Hanjung America, a subsidiary of South Korea-based battery manufacturer Hanjung NCS, will build its first US energy storage system (ESS) manufacturing facility in Huntington, Indiana, US.
Premium
March 9, 2026
Energy-Storage.news speaks with Isshu Kikuma, energy storage analyst at BloombergNEF (BNEF), ahead of the upcoming Energy Storage Summit USA.
March 5, 2026
Developer Avantus has closed a financing package of over US$300 million for the 100MWac/130MWdc solar, 400MWh BESS Kitt Solar and Energy Storage Project in Pinal County, Arizona, US.