China: Largest pumped hydro energy storage plant in the world fully operational

August 13, 2024
LinkedIn
Twitter
Reddit
Facebook
Email

The 12th and final turbine unit of a pumped hydro energy storage (PHES) plant in Hebei, China, has been put into full operation, making it the largest operational system in the world.

The 3.6GW Fengning Pumped Storage Power Station is located on the Luanhe River in Chengde City, Hebei Province, and is the largest PHES plant by installed capacity, state-owned outlet China Energy News said. The last units have completed trial operations and gone into full operation to generate electricity.

The PHES plant comprises 10 fixed-speed units and two variable-speed units, all 12 of which have a power rating of 300MW. The variable-speed units are the first in China, and enhance the flexibility of the PHES to adapt to grid load and stability requirements.

It was reported two years ago that the project with all 12 units had been completed but updates since appear to contradict that.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

For example, Austria-headquartered technology provider Andritz provided a variable speed unit for the plant and gave the following timeline:

  • 15 March 2023: Stator lifted into pit
  • 4 July 2023: Rotor lifted into pit
  • Mid-October 2023: The main installation work completed
  • Early November 2023: Dry commissioning completed
  • 10 November 2023: Wet commissioning officially commenced
  • 27 November 2023: First run of the unit
  • 10 December 2023: First synchronisation test in turbine mode completed

Andritz said that the project saw it take a much greater role in whole power plant equipment commissioning than it had ever done previously. The company is working on several other projects in China too, as well as as in Turkey, Brazil and Scotland (with the Cruachan plant, covered by our sister site Solar Power Portal).

At 3.6GW the Fengning plant is larger than what is widely reported to be the largest existing PHES plant in the world, the Bath County plant in Virginia, US, which has a power rating of 3,003MW.

Larger projects are underway elsewhere, including the 5GW Pioneer-Burdekin project in Queensland, Australia. The Queensland government just announced that 5 kilometres of core samples have been collected and solid granite will now be confirmed structurally through the site.

China brought 6.7GW of hydropower capacity into service last year according to the International Hydropower Association, of which 6.2GW was PHES. It intends to reach 80GW of PHES by 2027 and a total hydropower capacity of up to 120GW by 2030.

Read Next

December 16, 2025
Global average prices for turnkey battery storage systems fell by almost a third year-over-year, with sharp cost declines expected to continue.
Premium
December 16, 2025
A total of around 4.9GW/14GWh of grid-scale BESS entered commercial operations around the world last month, a 29% fall year-on-year owing to an unusually slow month in China.
December 15, 2025
A new battery energy storage system (BESS) cybersecurity whitepaper from consultancy firm The Brattle Group and cybersecurity solutions provider Dragos claims that a single 100MW/400MWh BESS outage could result in US$1.2 million in monthly losses.
December 12, 2025
System integrator Guoxia Technology has obtained approval for its main board listing on the Hong Kong Stock Exchange.