British Columbia and BC Hydro advance first ‘major’ BESS in Canadian province

LinkedIn
Twitter
Reddit
Facebook
Email

Canadian electric utility BC Hydro and the province of British Columbia (BC) are advancing the first major batteray energy storage system (BESS) project in the province.

Announced 20 July, BC Hydro and the province are launching a procurement process for a BESS project that will deliver “at least 100MW of battery storage capacity,” on Vancouver Island.

On Thursday, 30 July 2026, BC Hydro said it will issue a request for supplier qualifications to identify and pre-qualify experienced companies capable of designing and delivering the project.

Based on a review of responses received to the request for supplier qualifications, a pool of respondents will be invited to participate in a request for proposals (RFP) expected this year.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

BC Hydro expects to own and operate the BESS, helping to ensure it can be deployed when and where it is needed most to support its customers and maintain system reliability. BC Hydro further stated it will leverage private-sector expertise through a competitive process for design, construction and potentially long-term maintenance services.

After an evaluation of reliability, cost, environmental, and stakeholder factors, BC Hydro has chosen a site next to the Vancouver Island Terminal Substation near Duncan as the preferred location.

The utility said that utilising BC Hydro-owned land allows the project to be seamlessly integrated into the existing electricity infrastructure while reducing development impacts.

The facility is scheduled to become operational by 2030 and will support Vancouver Island’s electricity system as demand grows from expanding residential, commercial, and community development.

The Vancouver Island battery project is the first battery storage investment moving forward under BC Hydro’s Powering Growth plan. Powering Growth is BC Hydro’s strategy to address increasing electricity demand through conservation, optimisation of existing infrastructure, and investments in new renewable generation, transmission, and storage assets.

Under this plan, BC Hydro claims it has identified up to 500MW of potential battery storage capacity across British Columbia.

British Columbia, specifically Vancouver, is also home to a second-life BESS manufacturing hub from Moment Energy. The facility reached full-scale production in 2025 and produces the company’s Luna BESS, a 400kWh/1MWh unit that can be scaled into 10MWh that uses repurposed second-life electric vehicle (EV) batteries.

In 2024, Energy Plug Technologies and the Malahat Nation began construction on Canada’s first indigenous-led energy storage gigafactory in Mill Bay, British Columbia, with a target production output of 1GWh-per-year.

26 November 2026
9am GMT / 1pm GST
In this webinar, Florian Didier and Salomé Perperot from Clean Horizon share the approach they use when supporting IPPs through optimiser selection and contract negotiation across Europe. The presentation will be followed by a live Q&A session in which attendees can put their own questions to the speakers. Who should attend: IPPs and developers, asset owners and investors, lenders and financial advisors, and anyone involved in the commercial structuring of battery storage projects.
22 February 2027
InterContinental London - The O2, London, UK
The Future of Energy Storage Starts Here Three days in London where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into European storage, this is that room.

Read Next

November 20, 2026
EDF power solutions Australia has acquired the 250MW Holloway BESS project in New South Wales (NSW) from developer SynCo Global.
November 20, 2026
Australia committed a record 2.4GW of renewable energy projects to construction in the third quarter of 2026, while battery energy storage systems (BESS) committed in the quarter covered 13% of the new storage capacity needed by 2030.
Premium
November 19, 2026
As AI-driven data centre demand reshapes the US power landscape, BESS technology providers at RE+ highlighted an unexpected competitive advantage.
Sponsored
November 19, 2026
Pressure-sensitive adhesive (PSA) tape suppliers are testing dielectric materials for BESS lifetimes of 30 years or more, as rising pack voltages push tracking performance requirements higher.
November 19, 2026
The Bipartisan American Affordability and Jobs Act of 2026 (BAAJA) has been a popular topic of discussion at RE+ 2026 in Las Vegas, Nevada, US.