Amazon buys ready-to-build Oregon solar-plus-storage project from bankrupt developer Pine Gate

LinkedIn
Twitter
Reddit
Facebook
Email

Global tech giant Amazon has been approved as the buyer of the 1.2GW Sunstone solar project in Oregon, one of the largest solar PV projects in the US.

The Sunstone site was developed and previously owned by Pine Gate Renewables, the US independent power producer (IPP), which filed for bankruptcy in November 2025. It includes 1.2GW of solar PV and 1.2GW of battery energy storage system (BESS) capacity, which is ready to build, having received permitting and approvals from the Oregon Energy Facility Siting Council (EFSC).

Amazon’s acquisition was approved by the Bankruptcy Court for the Southern District of Texas, which granted its offer of US$83 million in cash via its specific project subsidiary, Oregon Solar I.

The move follows Amazon’s complaints back in November that an Oregon utility was not supplying sufficient power to its data centre projects in the state, where it has built numerous cloud computing data centres close to the banks of the Columbia River. Once fully operational, the Sunstone solar-plus-storage project will be one of the most significant renewable energy generation projects in the US.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Since declaring bankruptcy, Pine Gate’s roughly 10GW of project assets have been offered to the market, though the company says it has sufficient liquidity to continue operating in the meantime. 

To read the full version of this story, visit PV Tech.

Read Next

May 12, 2026
Ford Motor Company has officially launched its energy storage subsidiary, which the US automaker first announced late last year.
Premium
May 11, 2026
The US clean energy manufacturing industry is starting to undergo a wholesale restructuring and recapitalisation as companies look to reduce their exposure to numerous risks, including FEOC. 
Premium
May 11, 2026
Fluence’s share price rose sharply after its Q2 2026 financial results came out, with the company reaffirming full-year revenue and EBITDA guidance.
May 8, 2026
After reporting a record 112GW of global non-pumped hydro energy storage installations in 2025, BloombergNEF (BNEF) expects to see a 41% increase this year.
May 6, 2026
A quartet of Germany BESS project announcements: Green Flexibility has completed a project, Suncatcher has enlisted Statkraft to optimise three solar-plus-storage ones, SWB and Be.storaged are together building a system, while ArcelorMittal has enlisted EDF Power Solutions to do so.