Dominion Energy files IRP with plans to build 3.5GW of BESS in PJM over next 20 years

LinkedIn
Twitter
Reddit
Facebook
Email

US utility Dominion Energy plans to build 3.5GW of battery energy storage systems (BESS) over the next 20 years, according to its recently filed integrated resource plan (IRP).

On 15 October, Dominion filed a full comprehensive IRP with the North Carolina Utilities Commission (NCUC) and an interim update with the Virginia State Corporation Commission (SCC).

The 2026 IRP addresses three converging pressures: rising and shifting demand, evolving policy, and tightening capacity markets within PJM.

As the utility noted in its IRP, demand in Dominion Energy’s delivery zone continues to grow, with peaks shifting to winter mornings and summer evenings when weather-dependent resources produce less.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Meanwhile, new generation and transmission projects face longer timelines, interconnection constraints, supply-chain pressures, and siting challenges.

The IRP also reflects Virginia’s expanded storage mandate. In February, the Virginia General Assembly passed legislation to promote new energy storage investments by Dominion and Appalachian Power, the state’s primary utilities.

In April, Virginia Governor Abigail Spanberger signed the legislation into law. It requires Dominion to add 16,000MW of short-duration BESS capacity and 3,480MW of long-duration energy storage (LDES) capacity by 2045.

PJM conditions add further pressure. Dominion relies on PJM’s capacity market for resource adequacy, and the 2028/2029 Base Residual Auction cleared at the price cap, with committed capacity over 6,800MW below PJM’s requirement and reserve margin at just 14.4% against a 20% target — the second straight auction to clear short, reflecting load growth, generation retirements, resource delays, and updated ELCC accreditation standards.

The IRP stated, “Notably, the LDES targets do not become effective unless and until the SCC determines such technology is technically viable and that the construction, acquisition, or procurement targets are reasonably achievable.”

Dominion showed that its 2025 capacity resource mix was 39.7% natural gas, with renewables including solar, wind, hyrdo, and biomass at 11.3%, below Nuclear and coal. Renewable purchases were 6.5%, and separately, energy storage was 0.1%.

Dominion has petitioned for SCC approval of new company-owned and power purchase agreement (PPA) resources totalling 712MW of BESS capacity and nearly 5,000MW of solar in its annual Renewable Portfolio Standard (RPS) Development Plan proceeding. The utility currently has over 170MW of approved company-owned BESS projects and has approximately 50MW in operation. 459MW of BESS has also been approved under PPAs.

Dominion received approval from SCC to pilot three non-lithium-ion (Li-ion) projects, two of which are LDES projects. At the Darbytown Power Station in Virginia, two electrochemical systems will be tested, a zinc-hybrid battery from zinc battery storage player Eos Energy and an iron-air battery capable of discharging for up to 100 hours from US startup Form Energy.

Dominion’s preferred plan prioritises solar, wind, and BESS petitioned by 2035 and built by 2039, with remaining capacity selected on a least-cost basis.

For BESS, only the portion not requiring additional commission review (petitioned by 2030) is included upfront, with the rest selected on a least-cost basis — totalling 3.5GW. The plan also builds over 21GW of solar, exceeding Virginia Clean Economy Act (VCEA) requirements, plus three small modular reactor (SMR) sets starting in 2042 and 3.4GW of additional offshore wind.

To “preserve existing generation” and meet future reliability needs, the plan requires invoking the VCEA’s reliability exception and adding 8.9GW of gas-fired capacity.

26 November 2026
9am GMT / 1pm GST
In this webinar, Florian Didier and Salomé Perperot from Clean Horizon share the approach they use when supporting IPPs through optimiser selection and contract negotiation across Europe. The presentation will be followed by a live Q&A session in which attendees can put their own questions to the speakers. Who should attend: IPPs and developers, asset owners and investors, lenders and financial advisors, and anyone involved in the commercial structuring of battery storage projects.
2 February 2027
The Tower Hotel, London, UK
Solar & Storage Finance Europe Summit brings together the developers, investors and lenders financing European solar and storage projects. As grid constraints, curtailment and weaker capture prices put pressure on returns, the summit explores what makes projects bankable, how co-located storage changes the revenue case and where capital providers see investable opportunities. Attendees can compare how their peers structure projects and meet people who could help them move their own projects or investments forward.
22 February 2027
InterContinental London - The O2, London, UK
The Future of Energy Storage Starts Here Three days in London where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into European storage, this is that room.
20 April 2027
Renaissance Dallas at Plano Legacy West Hotel, Dallas, Texas, Dallas
Policy, Procurement and Power Demand: Defining the Next Chapter for Energy Storage. Two days in Dallas where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into US storage, this is that room.

Read Next

November 24, 2026
Flow battery company CMBLU Energy and California public utility Imperial Irrigation District (IID) have announced a 10MW/100MWh energy storage project that will mark IID’s first deployment of a non-lithium battery system.
November 24, 2026
The US Senate has passed the Bipartisan American Affordability and Jobs Act of 2026 (BAAJA), the permitting reform bill that has been a major source of industry discussion.
November 24, 2026
APA Group has started construction on its 72MW solar PV plant and 52MW/104MWh BESS at Mount Isa in north-west Queensland, Australia.
November 23, 2026
BESS account for 5.3GW of the 8.4GW of new projects added to Australia’s NEM since December 2025, according to AEMO.
November 20, 2026
Sodium-ion (Na-ion) is continuing to gain traction as a legitimate “major chemistry” — with CATL, BYD, and GM all committing to it — some developers, within and outside the US Na-ion space have argued that greater policy support should be directed toward advancing the technology.