Zelestra’s solar-plus-storage Spain offtake deal is ‘PPA 2.0’, firm says

LinkedIn
Twitter
Reddit
Facebook
Email

IPP Zelestra and utility EDP’s recent PPA deal for a solar-plus-storage project in Spain was the first of its kind in Europe and ‘moves the market forward’, a Zelestra executive told ESN Premium.

The companies signed a solar-plus-storage power purchase agreement (PPA) for a 170MWp solar, 400MWh battery energy storage system (BESS) project in Extremadura, Spain, in July 2025, claimed as the first of its kind. Co-located projects typically have a PPA in place for the solar PV portion, but not one that covers both the solar and BESS.

“As far as we know it was indeed the first in Europe. It is a PPA 2.0,” Zelestra’s chief product officer Stefano Breda told Energy-Storage.news Premium, adding that construction on the project is underway.

“It moves the market forward and responds to the challenges of delivering guaranteed supplies for customers in specific blocks of the day in markets that already have a high penetration of wind and solar.”

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Breda and Italy CEO Eliano Russo were discussing the firm’s recent BESS PPA and toll activity in Spain and Italy for an upcoming Q&A article.

Breda said that, when compared with conventional solar-only PPAs, the Spain deal mitigates price cannibalisation risk and generates a higher grid decarbonisation impact because the energy discharged by the battery will usually be displacing gas generating units.

When asked why we might only be seeing these kinds of deals in Europe now, when solar and BESS have been co-located for years, Breda said it’s a combination of market revenue and BESS pricing dynamics. Battery prices have fallen, as have the ancillary services that BESS project revenues have historically relied on. This has shifted the business model more towards solar load shifting, opening up the business case for deals like these.

It also opens up a revenue stream for BESS that might have its ancillary service market participation limited because of being co-located.

Zelestra’s experience in Chile, where it had already secured combined solar and BESS PPAs before the Spain announcement, helped it get this deal over the line quickly. It meant the company knew the main challenges it would need to overcome, both technical and engineering as well as commercial.

The shifting market dynamics in Spain have also enabled the addition of BESS to solar PV plants at no cost to the solar PV plant owners, the founder of a new firm called Lunas Energy told Energy-Storage.news in an interview in October 2025.

The Spanish grid-scale storage market has progressed rapidly in the past six months, with the government finalising recipients for an €840 million (US$981.61 million) grant package and large-scale project portfolios progressing to construction from Naturgy, Iberdrola and Turbo Energy. The discussion around the benefits of large-scale BESS on the grid has been particularly heightened since the Iberian blackout in April.

Energy-Storage.news publisher Solar Media is hosting the Energy Storage Summit EU 2026 in London, UK, on 24-25 February 2026 at the InterContinental London – The O2. See the official website for more details, including agenda and speaker lists.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.
2 December 2026
Italy
Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.

Read Next

Premium
September 10, 2026
We hear from Angus Gordon Lennox, chair of the Gore Street Energy Storage Fund (GSF), which faces a shareholder vote next week on its future. 
September 10, 2026
A roundup of large-scale BESS news from in and around the Nordic region, with Sweden-based Flower building a project in Germany, Volvo launching one in Sweden and Delta Capacity securing a toll for one in Finland. 
September 8, 2026
We are pleased to announce that we’re now working on the 2027 edition of the Energy Storage Report, our annual publication looking at the big trends shaping the industry. 
September 8, 2026
EDF Power Solutions has put a 150MW/600MWh BESS in Belgium into commercial operation while Engie has started building a 74MW/296MWh project. 
September 8, 2026
Aukera has closed a €460 million (US$534.23 million) structured credit facility to advance its project pipeline in five European markets.