IPP Zelestra and power firm and utility EDP have agreed two new hybrid power purchase agreements (PPAs) in Spain, adding 181MWdc of solar and 462MWh BESS to their existing co-operation. 

The companies have agreed combined solar-plus-storage power purchase agreements (PPAs) for Zelestra’s Pedroso and Valkyria projects in Seville and Casta la Mancha respectively. Zelestra is the project owner while EDP is the offtaker. 

Pedroso pairs 31MWdc of solar with a 25MW/100MWh battery energy storage system (BESS) while Valkyria pairs 150MWdc of solar with 90.45MW/362MWh of BESS. 

It brings the total BESS capacity in Spain covered by a hybrid PPA between the two companies to 1,022MWh, following deals announced in April 2026 (Pizarosso) and July 2025 (Trujillo). 

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The Pedroso, Valkyria and Pizarosso projects are existing PV plants which the PPA enables the addition of BESS to, while Trujillo is a greenfield solar and storage project unlocked by the PPA. 

The potential of BESS to enable independent power producers (IPP) to offer ‘flat curve’ price PPAs to offtakers has been much discussed, but contracts to this end are still relatively new. 

Zelestra’s last year was claimed as the first combined solar and storage PPA in Europe. Chief product officer Stefano Breda discussed it with Energy-Storage.news shortly after, calling it ‘PPA 2.0’. 

Zelestra has made long-term tolls a key part of its BESS strategy, and has possibly been the first to market with structures in Italy and Germany. 

Last month it signed a solar-plus-storage hybrid PPA with steel manufacturer Salzgitter Flachstahl in Germany, one of the first structures of that scale (147MW solar, 273MWh BESS) in the country. A month earlier it agreed a similarly sized standalone BESS toll with Centrica Energy. 

In Italy, it has entered into tolls for its BESS capacity with power firms Axpo, EnBW and BKW all for standalone BESS projects. Its Italy CEO Eliano Russo also discussed these and how the private toll space in Italy was enabled by the MACSE auction in 2025. 

Jaime Burguete, CEO of Zelestra in Spain, said: “Zelestra and EDP have built something together that is unique in the Spanish market: a commercial partnership that is unlocking large-scale storage capacity that will benefit the wider energy system. These four hybrid projects show that energy storage is bankable in Spain, and we expect this segment of the market to be the main growth area in the years ahead. It also means that every megawatt-hour moved into the evening or early morning is clean power the system would otherwise have had to find elsewhere.”

Breda said at the time of our interview that Spain-headquartered Zelestra has been able to use its experience in Chile, where hybrid PPAs are established, in pioneering the structure in Europe. It completed a 1GWh BESS there earlier this year. 

2 December 2026
Italy
Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.
22 February 2027
InterContinental London - The O2, London, UK
The Future of Energy Storage Starts Here Three days in London where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into European storage, this is that room.

Read Next

Premium
November 13, 2026
Floors are increasingly the offtake structure of choice in the UK market, and the contracting for them is beginning to standardise, industry experts said.
November 12, 2026
AirTrunk has signed an exclusivity agreement with European Energy Australia covering more than 800MWh of battery storage in NSW.
November 11, 2026
Envision Energy will supply its Gen 8 BESS platform for ju:niz Energy’s 442MWh Smareg 13 project in Bavaria, Germany.
November 11, 2026
Delta and partner Samsung Vista C&I Australia have lodged an EIS for an 800MWh BESS at the Vales Point Power Station site in NSW.
November 10, 2026
Power firms RWE and BNZ have both announced construction on large-scale BESS projects in Italy, all-in-all totalling nearly 500MWh of capacity.