Younicos to design 49MW Centrica battery as technology ‘emerges from demonstrator’ projects

December 14, 2016
LinkedIn
Twitter
Reddit
Facebook
Email

Younicos’ experience in utility-scale storage projects in the UK extends to the 6MW Leighton Buzzard demonstrator (pictured) it participated in. Image: RES.
Battery storage specialist Younicos has been selected by Centrica to design the 49MW battery storage project that was last week awarded a 15-year Capacity Market contract.

The battery, to be built on the site of a former coal-fired power station in Roosecote, Cumbria, is to be owned and operated by Centrica, but the energy giant has selected Younicos to design the system, which is to be completed by winter 2018.

The sophisticated, lithium-ion based system will be capable of responding to fluctuations in energy demand in less than a second. It will be aided by software designed and developed by Younicos for batteries used in such applications.

Speaking to Energy Storage News, Younicos spokesman Philip Hiersemenzel said the system will be “one of the most sophisticated” batteries in the world when it is complete.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

“It really underscores the versatility of what batteries can do and what they can do for the grid, for secure energy supplies and also for the people that operate them,” he said.

The Roosecote project is to use architecture developed off the back of Younicos’ participation in both Europe’s first commercial battery project in Schewin, Germany, and the software and controls it provided for UK Power Networks’ 6MW demonstrator project in Leighton Buzzard.

Hiersemenzel is, however, of the belief that the UK market is now emerging from the stage at which utility-scale batteries are considered demonstration projects, with the recent EFR and Capacity Market tender results providing ample evidence of confidence in the technology.

“I think the technology is really moving from being a demonstrator and into the market place. That’s become clear. We see the UK rapidly moving towards the commercialisation of batteries. It’s no longer a question as to whether they’re viable, it’s how to best deploy them,” he said.

At 49MW the battery stands to be the largest in the UK and among the largest in the world. This, Hiersemenzel said, would present its own challenges, but he is confident that Younicos has garnered the experience and requisite knowledge to see the project through, adding: “It reflects what we’ve learned over the years and what the market needs in terms of technical requirements and how best to handle the batteries.”

Read Next

November 19, 2025
Swedish renewable energy developer OX2 has formally taken ownership of the 1.2GW Dinner Hill Wind Farm and the co-located 400MWh Harvest Battery Energy Storage System (BESS) in Western Australia.
November 17, 2025
Rondo Energy and SCG Cleanergy have commenced operation of Southeast Asia’s first industrial thermal battery energy storage system (BESS) at SCG’s cement plant in Saraburi, Thailand.
November 17, 2025
Australia’s DCCEEW has announced that the Capacity Investment Scheme Tender 8 will launch later this month seeking 16GWh of energy storage.
November 14, 2025
BESS and flexible generation provider Statera Energy has secured £235 million (US$309 million) in debt financing for its 680MW/1,360MWh Carrington BESS project in Manchester, UK.
Premium
November 13, 2025
On 4 September, US Immigration and Customs Enforcement (ICE), along with multiple other law enforcement organisations, raided Hyundai Motor and LG Energy Solution’s electric vehicle (EV) battery cell plant in Ellabell, Georgia, US.