250MW/1,000MWh Ontario BESS begins commercial operations, potential expansion ahead

LinkedIn
Twitter
Reddit
Facebook
Email

US-headquartered clean energy solutions provider Ameresco’s joint venture (JV) with power producer Atura Power, has begun commercial operations at a 250MW/1,000MWh energy storage project in Ontario, Canada.

The Napanee battery energy storage system (BESS) project’s operational status was announced 19 May by Ontario’s minister of Energy and Mines, Stephen Lecce. The project was reportedly on budget and approximately five weeks ahead of schedule.

In 2023, Napanee BESS Inc, the JV, announced it was a winner in the Ontario Independent Electricity System Operator (IESO) Long-Term 1 (LT1) competitive tender.

LT1, at the time, resulted in the largest BESS capacity procurement in the country’s history, awarding over 850MW of BESS capacity contracts across two tranches during May and June of 2023.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

LT2 was launched in July 2025, it targeted 3TWh of energy generation, alongside 600MW of new capacity resources.

Earlier this month, IESO launched its Long Lead-Time request for proposal (LLT RFP), which looks to procure up to 800MW of long-duration energy storage (LDES).

Ameresco holds a 10.1% interest in the development JV and separately contracted to provide engineering, construction, and other unspecified “expertise” for the BESS installation.

Atura Power, a subsidiary of provincially-owned Ontario Power Generation, developed the Napanee project.

According to Lecce’s announcement, Napanee is valued at CA$600 million (US$435 million), and includes 284 battery storage units, transformer stations, transmission connection facilities and ancillary components, storing electricity from Ontario’s nuclear facilities during periods of low demand and returning that stored power to the system when demand increases.

Notably, the project utilised Ontario’s local supply chain by sourcing 72 medium voltage transformers built by manufacturing company Stein Industries in London, Ontario. The transformers were purchased through Nbisiing Power, an Indigenous-owned electrical equipment reseller operating in Nipissing First Nation.

Additionally, the development and construction of the Napanee project supported 120 jobs, including skilled trades, engineering, transportation, and equipment manufacturing roles.

Atura Power is also proposing another project at the site, the Napanee BESS Phase 2, which would be located next to the existing Napanee BESS project, with a capacity of 300MW/2,400MWh.

Napanee BESS Phase 2 is being proposed through the IESO LT2 procurement. An award through the LT2 would be announced 16 June.

According to the IESO, “the first Window of the Energy Stream of the LT2 RFP has now concluded. The IESO has executed contracts with 13 Selected Proponents, totaling 1,115.10MW of Maximum Contract Capacity and an aggregate Expected Annual Imputed Production of 2.37TWh. The capacity stream of the LT2 RFP is still currently active, and Proposals are being evaluated.”

In April, Quebec-based IPP Boralex and Six Nations of the Grand River Development Corporation (SNGRDC) announced the closing of a US$145.12 million financing for a 125MW/500MWh BESS in Oxford County, Ontario. That project was also awarded through the LT1 process.

Earlier this year, in the US, Amersco completed the second and third in a series of long-term debt financings for projects under a previously announced private shelf facility, provided by financial institution CounterpointeSRE and investment firm Barings, and concurrently transferred certain of the projects’ related investment tax credits (ITCs).

The company claimed that the facility with CounterpointeSRE and Barings streamlined its execution of multiple financings, driving consistency and scale across its pipeline of standalone energy storage and solar‑plus‑storage projects.

26 November 2026
9am GMT / 1pm GST
In this webinar, Florian Didier and Salomé Perperot from Clean Horizon share the approach they use when supporting IPPs through optimiser selection and contract negotiation across Europe. The presentation will be followed by a live Q&A session in which attendees can put their own questions to the speakers. Who should attend: IPPs and developers, asset owners and investors, lenders and financial advisors, and anyone involved in the commercial structuring of battery storage projects.
22 February 2027
InterContinental London - The O2, London, UK
The Future of Energy Storage Starts Here Three days in London where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into European storage, this is that room.

Read Next

November 20, 2026
EDF power solutions Australia has acquired the 250MW Holloway BESS project in New South Wales (NSW) from developer SynCo Global.
November 20, 2026
Australia committed a record 2.4GW of renewable energy projects to construction in the third quarter of 2026, while battery energy storage systems (BESS) committed in the quarter covered 13% of the new storage capacity needed by 2030.
Premium
November 19, 2026
As AI-driven data centre demand reshapes the US power landscape, BESS technology providers at RE+ highlighted an unexpected competitive advantage.
Sponsored
November 19, 2026
Pressure-sensitive adhesive (PSA) tape suppliers are testing dielectric materials for BESS lifetimes of 30 years or more, as rising pack voltages push tracking performance requirements higher.
November 19, 2026
The Bipartisan American Affordability and Jobs Act of 2026 (BAAJA) has been a popular topic of discussion at RE+ 2026 in Las Vegas, Nevada, US.