Wärtsilä completes delivery of 1,038 Quantum units to 1,400MWh Wooreen BESS in Australia

LinkedIn
Twitter
Reddit
Facebook
Email

All 1,038 Wärtsilä Quantum battery units have been delivered and installed at EnergyAustralia’s 1,400MWh Wooreen battery energy storage system (BESS) in Victoria’s Latrobe Valley, Australia.

Balance-of-plant contractor Zenviron confirmed the milestone on LinkedIn, describing the delivery of the 1,038th and final unit as “a fantastic achievement by the entire team.”

The project now moves into the remaining commissioning and grid connection works ahead of commercial operations, which Wärtsilä and Australian energy generator-retailer EnergyAustralia have targeted for 2027.

The Wooreen BESS is sized at 350MW/1,474MWh with 4-hours of storage duration. The project is being built adjacent to EnergyAustralia’s Jeeralang Power Station in the Latrobe Valley and is designed to enter service before the retirement of the Yallourn coal-fired power station, which is scheduled to close in mid-2028.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Finnish marine and energy technology group Wärtsilä was contracted to supply the BESS solution in a deal booked in Q4 2024 and announced in February 2025, covering engineering design, supply, commissioning and a 15-year service agreement.

The system uses Wärtsilä’s Quantum High Energy hardware and the company’s GEMS Digital Energy Platform and is designed to operate in grid-forming mode, enabling it to provide synthetic inertia and faster response times to stabilise the grid as coal-fired generation retires from the Victorian system.

When Wärtsilä launched the Quantum High Energy product in late 2023, the company said it delivered 9% greater energy density than the previous generation through the use of 306Ah lithium-ion cells, alongside fire safety improvements including active dehumidification, prefabricated fire walls between units and a dual sprinkler system.

That higher energy density directly reduces the number of units required per site and, by extension, the footprint and logistics complexity of delivering a project at Wooreen’s scale, where 1,038 individual units have now been received, staged, and installed.

In July 2025, EnergyAustralia sold a 50% share in the 1,400MWh Wooreen BESS to Thailand-based energy firm Banpu Public Company. The deal cost in the region of AU$700 million (US$490 million), with Banpu to provide an equity injection of AU$110 million.

A project built in layers

The construction programme at Wooreen has involved multiple contractors working across parallel workstreams since the project broke ground in February 2025, when EnergyAustralia started construction on the 350MW/1,400MWh BESS days after reaching financial close, with Victorian Energy Minister Lily D’Ambrosio attending the commencement ceremony.

Zenviron, the joint venture between engineering group Monadelphous and renewable energy developer ZEM Energy, was awarded the balance-of-plant contract covering design, construction, installation and commissioning.

The Wooreen project received support in the first round of the Australian government’s Capacity Investment Scheme (CIS), which has been the primary federal mechanism for underwriting new storage investment across the National Electricity Market (NEM).

EnergyAustralia’s broader storage portfolio extends beyond Wooreen, with the company having also reached financial close on the 50MW/250MWh Hallett BESS in South Australia in February 2026, a project using NHOA Energy as battery integrator and targeting commercial operations by mid-2027.

The completion of battery installations at Wooreen brings the project to the threshold of commissioning, the phase in which individual units are progressively energised, tested and integrated into the site’s control systems before grid connection is established.

For a project of 1,038 units, that process is typically sequenced in blocks rather than all at once, meaning partial capacity is likely to be available before the full 350MW rating is confirmed by AEMO.

Never miss an Australian energy storage story. Sign up for our Australia newsletter and get the latest project announcements, policy updates and market analysis delivered directly to you.

Our publisher, Solar Media (part of Informa Group), will host the Battery Asset Management Summit Australia 2026 on 25-26 August at Amora Hotel Jamison in Sydney. You can find out more about the Summit on the official website.

6 October 2026
Warsaw, Poland
The Energy Storage Summit Central Eastern Europe is set to return in September 2025 for its third edition, focusing on regional markets and the unique opportunities they present. This event will bring together key stakeholders from across the region to explore the latest trends in energy storage, with a focus on the increasing integration of energy storage into regional grids, evolving government policies, and the growing need for energy security.
3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

September 21, 2026
A US battery storage pilot sponsored by tech giant Google has demonstrated how batteries can capture surplus renewable energy and deliver it during hours with greater fossil generation.
September 21, 2026
The US energy storage industry is targeting 225GW/1TWh of storage deployment by the end of 2032, according to an analysis published by the Energy Storage Coalition (ESC).
September 21, 2026
The Tailem Bend BESS 3 in South Australia and Wooreen BESS in Victoria have both entered the AEMO Market Management System (MMS).
September 21, 2026
Flow Power has broken ground on its 100MW/223MWh Bennetts Creek BESS in Victoria, its first large-scale standalone BESS project.
September 18, 2026
In this US news roundup, Eos has received an advance on its DOE loan, FlexGen and Lighshift have partnered on 16 BESS projects, and Georgia Power has energised a 128MW BESS.