Wärtsilä completes delivery of 1,038 Quantum units to 1,400MWh Wooreen BESS in Australia

LinkedIn
Twitter
Reddit
Facebook
Email

All 1,038 Wärtsilä Quantum battery units have been delivered and installed at EnergyAustralia’s 1,400MWh Wooreen battery energy storage system (BESS) in Victoria’s Latrobe Valley, Australia.

Balance-of-plant contractor Zenviron confirmed the milestone on LinkedIn, describing the delivery of the 1,038th and final unit as “a fantastic achievement by the entire team.”

The project now moves into the remaining commissioning and grid connection works ahead of commercial operations, which Wärtsilä and Australian energy generator-retailer EnergyAustralia have targeted for 2027.

The Wooreen BESS is sized at 350MW/1,474MWh with 4-hours of storage duration. The project is being built adjacent to EnergyAustralia’s Jeeralang Power Station in the Latrobe Valley and is designed to enter service before the retirement of the Yallourn coal-fired power station, which is scheduled to close in mid-2028.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Finnish marine and energy technology group Wärtsilä was contracted to supply the BESS solution in a deal booked in Q4 2024 and announced in February 2025, covering engineering design, supply, commissioning and a 15-year service agreement.

The system uses Wärtsilä’s Quantum High Energy hardware and the company’s GEMS Digital Energy Platform and is designed to operate in grid-forming mode, enabling it to provide synthetic inertia and faster response times to stabilise the grid as coal-fired generation retires from the Victorian system.

When Wärtsilä launched the Quantum High Energy product in late 2023, the company said it delivered 9% greater energy density than the previous generation through the use of 306Ah lithium-ion cells, alongside fire safety improvements including active dehumidification, prefabricated fire walls between units and a dual sprinkler system.

That higher energy density directly reduces the number of units required per site and, by extension, the footprint and logistics complexity of delivering a project at Wooreen’s scale, where 1,038 individual units have now been received, staged, and installed.

In July 2025, EnergyAustralia sold a 50% share in the 1,400MWh Wooreen BESS to Thailand-based energy firm Banpu Public Company. The deal cost in the region of AU$700 million (US$490 million), with Banpu to provide an equity injection of AU$110 million.

A project built in layers

The construction programme at Wooreen has involved multiple contractors working across parallel workstreams since the project broke ground in February 2025, when EnergyAustralia started construction on the 350MW/1,400MWh BESS days after reaching financial close, with Victorian Energy Minister Lily D’Ambrosio attending the commencement ceremony.

Zenviron, the joint venture between engineering group Monadelphous and renewable energy developer ZEM Energy, was awarded the balance-of-plant contract covering design, construction, installation and commissioning.

The Wooreen project received support in the first round of the Australian government’s Capacity Investment Scheme (CIS), which has been the primary federal mechanism for underwriting new storage investment across the National Electricity Market (NEM).

EnergyAustralia’s broader storage portfolio extends beyond Wooreen, with the company having also reached financial close on the 50MW/250MWh Hallett BESS in South Australia in February 2026, a project using NHOA Energy as battery integrator and targeting commercial operations by mid-2027.

The completion of battery installations at Wooreen brings the project to the threshold of commissioning, the phase in which individual units are progressively energised, tested and integrated into the site’s control systems before grid connection is established.

For a project of 1,038 units, that process is typically sequenced in blocks rather than all at once, meaning partial capacity is likely to be available before the full 350MW rating is confirmed by AEMO.

Never miss an Australian energy storage story. Sign up for our Australia newsletter and get the latest project announcements, policy updates and market analysis delivered directly to you.

Our publisher, Solar Media (part of Informa Group), will host the Battery Asset Management Summit Australia 2026 on 25-26 August at Amora Hotel Jamison in Sydney. You can find out more about the Summit on the official website.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.
26 November 2026
9am GMT / 1pm GST
In this webinar, Florian Didier and Salomé Perperot from Clean Horizon share the approach they use when supporting IPPs through optimiser selection and contract negotiation across Europe. The presentation will be followed by a live Q&A session in which attendees can put their own questions to the speakers. Who should attend: IPPs and developers, asset owners and investors, lenders and financial advisors, and anyone involved in the commercial structuring of battery storage projects.
22 February 2027
InterContinental London - The O2, London, UK
The Future of Energy Storage Starts Here Three days in London where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into European storage, this is that room.

Read Next

November 2, 2026
Two Australian battery storage projects in Queensland and Victoria have entered federal environmental review, with AGL Energy and developer ACEnergy each submitting referrals under the same national process.
November 2, 2026
Sungrow will supply both the BESS and the grid-forming power conversion equipment for ENGIE’s Hazelwood BESS expansion in Victoria, Australia.
November 2, 2026
Australia’s grid-scale BESS fleet earned an estimated AU$37.62 million in the National Electricity Market (NEM) in October 2026.
Premium
October 30, 2026
Few grids illustrate the strain of America’s data centre boom more starkly than the PJM Interconnection.
October 30, 2026
Demand for 8-hour battery energy storage in Australia is “completely artificial” and relies on government underwriting, according to Tesla, which said asymmetric registration can help such projects earn more.