Developer Penso Power has signed a new agreement with global maritime group BW Group that will see the build-out of the former’s UK battery storage pipeline fully funded.

The pipeline of over 3GWh of large-scale battery storage projects are to be built over the next 3-5 years, with this including projects up to 350MW in connection capacity. The agreement will see Penso Power and BW Group become joint shareholders at the battery project level.

Additionally, BW Group is to invest directly into Penso Power to become a significant shareholder, with Erik Strømsø, managing director of BW Renewables and a member of BW Group’s executive committee joining Penso Power’s board of directors.

“BW Group’s commitment is a coming of age for the UK battery storage market: a blue-chip international company deploying very significant amounts of capital to build a substantial portfolio of large-scale battery storage projects in the UK,” said Richard Thwaites, chief executive of Penso Power.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“We view the deal – considerably larger than anything else seen in the UK to date – as transformational for ourselves and indeed the UK market,” he said.

Sister site Solar Power Portal asked Penso Power for clarity on the exact amount being invested, and was told the agreement is open-ended and as such, no exact figure is currently being given.

Penso Power already has experience in developing UK battery storage, with its 100MW Minety battery energy storage system (BESS) entering full operation in July. The site consists of two 50MW batteries, with plans in place to expand the site by a further 50MW. Sungrow supplied both NCM and LFP battery energy storage system solutions to the project, with these featuring high integration, therefore minimising the footprint, lowering the commissioning duration and lowering system cost by 5%.

Minety was funded by China Huaneng Group and CNIC Corporation, with Shell Energy Europe signing a multiyear offtake agreement in early 2020 for the site.

This story first appeared on Solar Power Portal.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

July 2, 2026
A roundup of recent large-scale BESS activity in the UK, with IPPs ContourGlobal, Zenobē and Revera buying or taking FID on three separate projects totalling 3.6GWh of capacity.
July 2, 2026
Singapore-headquartered clean energy developer Vena Energy has raised AU$1.4 billion (US$970 million) in green finance to support 614MW of solar PV capacity and 1,141MWh of battery energy storage systems (BESS) in Australia.
July 1, 2026
A lot of work and thought still needs to go into maximising the potential for co-location of solar and BESS technology, panellists at the Clean Power 2030 Summit said yesterday (30 June).
Premium
June 29, 2026
OptiGrid’s Sahand Karimi examines why state of charge & algorithm quality drove divergent outcomes during SA1’s AU$20,300/MWh price cap on 21 June.
June 26, 2026
UK energy regulator Ofgem has shortlisted 16 projects for the first ever long-duration energy storage (LDES) cap-and-floor scheme, totalling 7.6GW of capacity ranging from 8- to 22-hour durations.