TotalEnergies JV plans 2.7GW solar-plus-storage project to power Northern Territory green hydrogen hub

LinkedIn
Twitter
Reddit
Facebook
Email

A joint venture (JV) between TotalEnergies and Eren Groupe has submitted a 6GWh solar-plus-storage project for environmental approval in Australia’s Northern Territory (NT).

This marks the first phase of what is planned to be the region’s inaugural solar-powered green hydrogen production and export operation.

The Wak Wak Solar Farm, located approximately 48km southeast of Darwin in the Litchfield Local Government Area, features up to 2.7GWp of solar PV capacity paired with a 6GWh battery energy storage system (BESS).

The project has been referred under Australia’s Environment Protection and Biodiversity Conservation (EPBC) Act, with the proponent identifying potential impacts on seven EPBC-listed threatened species.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Darwin H2 Project Nominee, acting as trustee for the Darwin H2 Hub Project Trust, is developing the facility on behalf of TE H2, a joint venture dedicated to gigawatt-scale multi-energy projects globally. TotalEnergies holds an 80% stake in the venture, with Eren Groupe holding the remaining 20%.

The solar PV power plant is designed to generate renewable energy for the existing industry in the Greater Darwin Region and to power a planned green hydrogen production facility at the Middle Arm Precinct.

Meanwhile, the broader Darwin H2 Hub aims to produce more than 80,000 tonnes of hydrogen derived from renewable energy annually.

Site selection and environmental considerations

The project area spans up to 3,400 hectares, with a disturbance footprint of up to 2,500 hectares identified through extensive ecological surveys. Darwin H2 has incorporated 900 hectares of wildlife corridors between sections of the disturbance footprint, which will require ongoing management throughout the project’s operational life.

The site was deliberately selected in areas of compromised habitat quality to minimise impacts on biodiversity values.

According to the EPBC Act application, fire frequency mapping reveals that most of the project area has burned 20 or more times since 2000, with some northern sections experiencing late-season burns approximately 12 times during that period.

This highly detrimental fire regime has severely reduced the midstorey vegetation and contributed to widespread infestations of Gamba Grass, a declared weed under the Northern Territory’s Weeds Management Act.

The project design has avoided known sacred sites, flood-prone areas, high-quality vegetation, threatened species habitats, and threatened flora records.

Most of the project area sits on a perpetual pastoral lease, with smaller portions on freehold land. Access is proposed from the Arnhem Highway, with the exact route subject to consultation with relevant authorities and a traffic impact assessment.

Transmission infrastructure and staged development

While the solar PV power plant itself forms the core of this EPBC referral, the project is intrinsically linked to planned transmission infrastructure that would transmit renewable energy to the Middle Arm Precinct.

An overhead transmission line is planned to run within an existing Northern Territory government utilities corridor, approximately 30km long and 50 metres wide, forming part of the wider Territory Energy Link currently under design by the NT government.

The transmission line has been excluded from this environmental referral due to ongoing commercial negotiations and coordination with the NT government for use of the nominated utilities corridor.

Darwin H2 has indicated that ownership and operation of the overhead transmission line may ultimately rest with the NT government as a shared corridor accommodating multiple proponents and various types of public infrastructure.

The project is currently at the concept design stage, with the potential for staged development over its operational life.

Works will include land clearing and site preparation, construction of solar PV and BESS infrastructure, ongoing operation and maintenance, including periodic cleaning of solar arrays, and potential repowering after 30 years of operation before eventual decommissioning and site rehabilitation.

The Energy Storage Summit Australia 2026 will be returning to Sydney on 18-19 March. It features keynote speeches and panel discussions on topics such as the Capacity Investment Scheme, long-duration energy storage, and BESS revenue streams. ESN Premium subscribers receive an exclusive discount on ticket prices. 

To secure your tickets and learn more about the event, please visit the official website

9 June 2026
Stuttgart, Germany
Held alongside The Battery Show Europe, Energy Storage Summit provides a focused platform to understand the policies, revenue models and deployment conditions shaping Germany’s utility-scale storage boom. With contributions from TSOs, banks, developers and optimisers, the Summit explores regulation, merchant strategies, financing, grid tariffs and project delivery in a market forecast to integrate 24GW of storage by 2037.
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
15 September 2026
Berlin, Germany
Launching September 2026 in Berlin, Energy Storage Summit Germany is a new standalone event dedicated to Germany’s energy storage market. Bringing together investors, developers, policymakers, TSOs, manufacturers and optimisation specialists, the Summit explores the regulatory shifts, revenue models, financing strategies and technology innovations shaping large-scale deployment. With Germany targeting 80% renewables by 2030, it offers a focused platform to connect with the decision-makers driving the Energiewende and the future of utility-scale storage.

Read Next

June 5, 2026
Developer EDF power solutions North America and developer-operator Abu Dhabi Future Energy Company – Masdar, have entered into 15-year power purchase agreements (PPAs) for a California, US solar-plus-storage project.
June 5, 2026
Akaysha Energy’s Waratah Super Battery is now operating at 700MW and 1,680MWh following the successful return to service of High Voltage Transformer 2 (HVT2), the BlackRock-backed developer confirmed in a market update today (4 June).
June 5, 2026
Australia’s Victorian government has approved four new energy projects worth a combined AU$2.4 billion via its DFP, including 1,390MW of BESS.
Premium
June 4, 2026
Energy-Storage.news Premium speaks with Arnab Pal, executive director at nonprofit Deploy Action, about the company’s recent California polling results.
June 4, 2026
US solar manufacturer T1 Energy has entered into a definitive agreement to acquire vertically integrated battery energy storage system (BESS) company KORE Power.