Further details about Brazil’s largest battery storage project to date have been revealed including its integrators and equipment providers.

The inauguration of the 30MW/60MWh system took place last year, on the networks of transmission system operator (TSO) ISO CTEEP, as reported by Energy-Storage.news in November.

ISO CTEEP claimed it as the first large-scale battery energy storage system (BESS) on Brazil’s transmission grid. The project required a total US$27 million investment. The transmission operator is permitted by regulations to earn up to US$5 million revenues from the asset each year.

It will help increase hosting capacity to cope with expected increase in demand on a congested network enabling the TSO to defer from investing in a more expensive traditional transmission line, making this project an example of a ‘non-wires alternative’ or storage-as-a-transmission asset.  

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

It will also help reduce reliance on fossil fuel peaker plants, which can be among the most polluting and expensive generating units to run on the grid, despite typically having a low capacity factor through only coming into use infrequently during the year’s peak events.

The plant is sited at an ISO CTEEP substation in São Paulo.

US technology company Fractal EMS said yesterday that it worked on integrating the system, together with Brazilian energy storage solutions provider You.On, which was selected for the project through a competitive tender process.

Fractal EMS provided the energy management system (EMS) controls, SCADA and other components to system integrator You.On. Meanwhile You.On selected inverters from manufacturer Kehua, while the BESS is equipped with CATL’s liquid cooled battery storage solution.  

Fractal EMS CEO Daniel Crotzer said the Brazilian energy storage market “presents a significant growth opportunity,” claiming battery storage could “propel Brazil to 100% clean energy”.

You.On produced a short video ‘virtual 360° tour’ of the project (audio in Portuguese):

Read Next

October 29, 2025
German solar inverter manufacturer SMA has officially launched its system integrator subsidiary in Australia, with work underway on two battery storage projects.
Premium
October 22, 2025
John Zahurancik, Americas president at Fluence, discussed industry trends and policy directions with ESN Premium at this year’s RE+.
October 21, 2025
Wärtsilä Energy Storage’s new battery data analytics software platform aims to bring in-house what has until now been the domain of third-party providers.
October 16, 2025
During the opening address of Energy Storage Summit Latin America 2025, in Santiago, Chile, the Chilean Minister of Energy Diego Pardow Lorenzo said the country was most likely set to surpass its 2050 targets in 2027.
October 14, 2025
Spanish IPP Grenergy has begun construction on a 340MW solar project with 960MWh of energy storage in El Cabrero, located in Chile’s Biobío region. 

Most Popular

Email Newsletter