Further details about Brazil’s largest battery storage project to date have been revealed including its integrators and equipment providers.

The inauguration of the 30MW/60MWh system took place last year, on the networks of transmission system operator (TSO) ISO CTEEP, as reported by Energy-Storage.news in November.

ISO CTEEP claimed it as the first large-scale battery energy storage system (BESS) on Brazil’s transmission grid. The project required a total US$27 million investment. The transmission operator is permitted by regulations to earn up to US$5 million revenues from the asset each year.

It will help increase hosting capacity to cope with expected increase in demand on a congested network enabling the TSO to defer from investing in a more expensive traditional transmission line, making this project an example of a ‘non-wires alternative’ or storage-as-a-transmission asset.  

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

It will also help reduce reliance on fossil fuel peaker plants, which can be among the most polluting and expensive generating units to run on the grid, despite typically having a low capacity factor through only coming into use infrequently during the year’s peak events.

The plant is sited at an ISO CTEEP substation in São Paulo.

US technology company Fractal EMS said yesterday that it worked on integrating the system, together with Brazilian energy storage solutions provider You.On, which was selected for the project through a competitive tender process.

Fractal EMS provided the energy management system (EMS) controls, SCADA and other components to system integrator You.On. Meanwhile You.On selected inverters from manufacturer Kehua, while the BESS is equipped with CATL’s liquid cooled battery storage solution.  

Fractal EMS CEO Daniel Crotzer said the Brazilian energy storage market “presents a significant growth opportunity,” claiming battery storage could “propel Brazil to 100% clean energy”.

You.On produced a short video ‘virtual 360° tour’ of the project (audio in Portuguese):

14 October 2025
InterContinental, Santiago, Chile
We are excited to bring the industry together for the fourth edition of the Energy Storage Summit Latin America on 14-15 October in Santiago, Chile. The Summit has become a meeting place for IPPs and developers, investors, financiers and banks, utilities, consultancies, software providers, and manufacturers who are setting high standards in the Latin American energy storage sector.

Read Next

Premium
August 13, 2025
FlexGen “felt compelled to step up” and ensure the continuity of operation of the more than 11GWh of assets deployed by acquisition target Powin.
August 12, 2025
Fluence expects to hit the lower end of its previously issued revenue guidance for the 2025 financial year due to delays in ramping up at US production sites.
August 11, 2025
A 535MW fleet of aggregated household battery storage systems, including Tesla Powerwalls, effectively reduced net load on the California grid in a recent test event.  
Sponsored
August 11, 2025
One of the world’s major players in solar PV is also becoming a well-known name in the energy storage system (ESS) space.
August 7, 2025
Software-focused energy storage system integrator FlexGen’s bid to acquire assets from bankrupt rival Powin has been approved in court.

Most Popular

Email Newsletter