Further details about Brazil’s largest battery storage project to date have been revealed including its integrators and equipment providers.

The inauguration of the 30MW/60MWh system took place last year, on the networks of transmission system operator (TSO) ISO CTEEP, as reported by Energy-Storage.news in November.

ISO CTEEP claimed it as the first large-scale battery energy storage system (BESS) on Brazil’s transmission grid. The project required a total US$27 million investment. The transmission operator is permitted by regulations to earn up to US$5 million revenues from the asset each year.

It will help increase hosting capacity to cope with expected increase in demand on a congested network enabling the TSO to defer from investing in a more expensive traditional transmission line, making this project an example of a ‘non-wires alternative’ or storage-as-a-transmission asset.  

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

It will also help reduce reliance on fossil fuel peaker plants, which can be among the most polluting and expensive generating units to run on the grid, despite typically having a low capacity factor through only coming into use infrequently during the year’s peak events.

The plant is sited at an ISO CTEEP substation in São Paulo.

US technology company Fractal EMS said yesterday that it worked on integrating the system, together with Brazilian energy storage solutions provider You.On, which was selected for the project through a competitive tender process.

Fractal EMS provided the energy management system (EMS) controls, SCADA and other components to system integrator You.On. Meanwhile You.On selected inverters from manufacturer Kehua, while the BESS is equipped with CATL’s liquid cooled battery storage solution.  

Fractal EMS CEO Daniel Crotzer said the Brazilian energy storage market “presents a significant growth opportunity,” claiming battery storage could “propel Brazil to 100% clean energy”.

You.On produced a short video ‘virtual 360° tour’ of the project (audio in Portuguese):

Read Next

November 27, 2025
A joint venture (JV) between EDF and developer AME has begun construction of large-scale battery and solar photovoltaic (PV) projects in Chile, with 2GWh storage capacity.
November 26, 2025
We caught up with the president of system integrator PotisEdge following news of its acquisition by Longi, which marks the Chinese solar PV giant’s move into the energy storage industry.
November 24, 2025
Fluence, Energy Dome and EDF each scored consecutive wins in prestigious categories at the Energy Storage Awards 2025 in London.
November 21, 2025
The development of data centres has emerged as a possible lifeline for ongoing projects in the battery energy storage system (BESS) industry.
Premium
November 20, 2025
The battery storage industry’s race for higher energy density should be put into a site-level perspective, rather than focusing solely on larger cells.