Scotland’s first utility-scale battery brought online to deliver sub-second balancing

By David Pratt
LinkedIn
Twitter
Reddit
Facebook
Email
Helen Mahy, chairman of TRIG and Gavin McAlpine, chairman of RES, show Scotland’s minister for trade, investment and innovation, Ivan McKee, centre, around the Broxburn Energy Storage facility. Image: RES.

Scotland’s first utility-scale battery storage facility has been officially opened today, having begun delivering sub-second balancing services to National Grid at the end of June under a bespoke agreement secured before the hotly contested Enhanced Frequency Response (EFR) auction of 2016.

The 20MW Broxburn Energy Storage facility was built by RES, which had sold the project to The Renewables Infrastructure Group (TRIG) in August last year for £20 million. It was the first project to have been acquired by TRIG and RES’ fourth in the UK, with the company now managing the site.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

Richard Crawford, director of infrastructure at TRIG’s investment manager InfraRed Capital Partners, said it was “an exciting day for the company” to see its first battery storage project completed.

Testing of the project, which uses batteries from Samsung SDI, commenced in May, enabling battery commissioning to be completed. This was followed by final testing under the EPC construction contract, which completed on 30 June when the battery began to deliver its contracted service to National Grid.

The project had secured an initial four-year bespoke bilateral agreement to provide dynamic, two-way import and export sub-second balancing services to National Grid. Sister title Solar Power Portal was told in 2017 that revenues over the contract are substantially based on pre-determined, RPI-indexed availability payments.

Such a bespoke agreement was no longer available when National Grid moved to a tender auction model for EFR services, when almost 1GW of storage projects competed to win 200MW in available contracts.

Opening the site today, Scotland’s minister for trade, investment and innovation Ivan McKee said: “I am very pleased to have the chance to open the Broxburn Energy Storage project today, which is Scotland’s first sub-second response energy storage project.

“A welcome addition to Scotland’s low carbon energy system, projects such as this one can increase system flexibility and create opportunities for the further decarbonisation of Scotland’s economy.”

Both TRIG and RES added that the battery would allow for greater levels of renewable energy to be brought onto the UK’s energy system by helping to avoid the cost of new grid infrastructure.

Rachel Ruffle, RES’ managing director, said: “We believe that this project will play an important role in demonstrating this and will encourage policymakers and regulators to accelerate the removal of barriers to wider deployment of energy storage in the UK.”

Broxburn represents Scotland’s largest energy storage facility, with a 2MW battery installed at a power station in Orkney thought to be the next largest. This is followed by the 1MW/1.3MWh ‘Batwind’ project, connected to an offshore floating wind farm, which was brought online by Younicos in July this year. 

11 November 2025
San Diego, USA
The 2024 Summit included innovative new features including a ‘Crash Course in Battery Asset Management’, Ask-Me-Anything formats and debate-style sessions. You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

March 27, 2025
A panel of developers, operators, OEMs and consultants discussed the different government approaches in Europe to ensuring long-term deployment of energy storage with revenue and capex support schemes, at last month’s Energy Storage Summit EU 2025.
March 27, 2025
Mark Croudace, executive representative of the LDES Council, questioned what technologies will join lithium-ion on the energy storage podium.
March 26, 2025
Oil and gas major TotalEnergies has taken a final investment decision (FID) and started construction on a further six BESS projects in Germany, with Saft to provide the battery technology.
March 26, 2025
Fluence will use its AI-powered bidding optimisation software Mosaic to co-optimise Gentari’s 172MW Maryvale solar+BESS site in Australia.
March 25, 2025
LG Energy Solution has confirmed that it will manufacture the batteries for a 263MW/900MWh BESS project in Poland at its plant in Wroclaw, in the southwest of the country.

Most Popular

Email Newsletter