Scotland’s first transmission system-connected battery storage project underway

By Molly Lempriere
LinkedIn
Twitter
Reddit
Facebook
Email

Zenobē has begun construction of its 50MW/100MWh battery storage asset in Scotland, said to be the first transmission connected battery in the country.

The project in Wishaw, North Lanarkshire was first announced in May 2021 and, having reached financial close, is now expected to go live by the end of 2022.

It is being financed by Santander UK. Zenobē is working with Centrica as the route to market provider, Fluence as the battery energy storage system (BESS) supplier and H&MV as the principal designer and contractor.

“This project demonstrates real innovation,” said James Basden, co-founder and director of Zenobē.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“Scotland is leading the world in its move to renewable energy and Zenobē is proud to be providing the critical infrastructure needed for the country’s clean energy transition. Alongside our partners Fluence, Centrica, H&MV and Santander UK, we’re increasing flexibility of power supply for Glasgow and the wider network and so allowing a greater uptake of renewable energy.”

The battery will be the first in a series of major battery flexibility projects, he added, forming part of the company’s plans to invest roughly £500 million (US$624.81 million) in Scotland in the next five years.

Once operational, Centrica will optimise the battery and provide access to a variety of revenue streams for the asset.

 “We’re delighted to support Zenobē with multi-market optimisation services,” said Arno Van Mourik, director of Centrica Business Solutions International.

“We’ll leverage our proprietary FlexPond platform and trading capabilities to be in the right market at the right time, unlocking greater returns over the lifetime of the project, while supporting the decarbonisation of our power system.”

The Wishaw battery asset will also be used as part of National Grid ESO’s Constraints Management pathfinder, helping to identify and tackle challenges around transmission capacity in the region. Zenobē said that it will be the first battery in the UK to act as a flexibility tool to manage such constraints.

Zenobē is continuing to build out its battery energy storage portfolio in the UK, having also begun construction of its 100MW/107MWh battery at Capenhurst, near Chester in June 2021. This too was financed by Santander UK, following a first-of-a-kind facility between Zenobe and Santander UK in 2019.

This story first appeared on Solar Power Portal.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

June 8, 2026
To avoid pitfalls that harm BESS investments, developers must sign well-structured contracts, writes Intertek CEA’s Yilin Huang.
June 3, 2026
Queensland Investment Corporation has opened a formal call for proposals under the state government’s AU$200 million North West Energy Fund.
Premium
June 2, 2026
Energy-Storage.news Premium speaks with Ravi Manghani at Anza Renewables about why some BESS developers are forgoing the ITC altogether.
June 2, 2026
This special Japanese market roundup covers large-scale BESS project announcements from PowerX, Eku Energy and SMFL.
June 1, 2026
That’s according to Benedikt Deuchert, head of business development and regulatory affairs for German battery energy storage system (BESS) developer and EPC firm Kyon Energy.