Zenobē has begun construction of its 50MW/100MWh battery storage asset in Scotland, said to be the first transmission connected battery in the country.

The project in Wishaw, North Lanarkshire was first announced in May 2021 and, having reached financial close, is now expected to go live by the end of 2022.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

It is being financed by Santander UK. Zenobē is working with Centrica as the route to market provider, Fluence as the battery energy storage system (BESS) supplier and H&MV as the principal designer and contractor.

“This project demonstrates real innovation,” said James Basden, co-founder and director of Zenobē.

“Scotland is leading the world in its move to renewable energy and Zenobē is proud to be providing the critical infrastructure needed for the country’s clean energy transition. Alongside our partners Fluence, Centrica, H&MV and Santander UK, we’re increasing flexibility of power supply for Glasgow and the wider network and so allowing a greater uptake of renewable energy.”

The battery will be the first in a series of major battery flexibility projects, he added, forming part of the company’s plans to invest roughly £500 million (US$624.81 million) in Scotland in the next five years.

Once operational, Centrica will optimise the battery and provide access to a variety of revenue streams for the asset.

 “We’re delighted to support Zenobē with multi-market optimisation services,” said Arno Van Mourik, director of Centrica Business Solutions International.

“We’ll leverage our proprietary FlexPond platform and trading capabilities to be in the right market at the right time, unlocking greater returns over the lifetime of the project, while supporting the decarbonisation of our power system.”

The Wishaw battery asset will also be used as part of National Grid ESO’s Constraints Management pathfinder, helping to identify and tackle challenges around transmission capacity in the region. Zenobē said that it will be the first battery in the UK to act as a flexibility tool to manage such constraints.

Zenobē is continuing to build out its battery energy storage portfolio in the UK, having also begun construction of its 100MW/107MWh battery at Capenhurst, near Chester in June 2021. This too was financed by Santander UK, following a first-of-a-kind facility between Zenobe and Santander UK in 2019.

This story first appeared on Solar Power Portal.

12 November 2024
San Diego, USA
As we see more storage projects become operational, the big question is “how to maximize your assets?” This event will prepare the industry for the road ahead, looking at the core fundamentals of asset management, understanding operational challenges, along with the latest optimization and software development. You can expect to meet and network with all the key industry players from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

June 25, 2024
Startup Capalo AI will optimise a Finland BESS project owned by investor Ardian while Merus Power, which is providing the BESS for that project, has received a separate order from Switzerland’s Alpiq for a similarly sized one.
June 25, 2024
Elements Green has secured planning permission for its Staythorpe battery energy storage system (BESS) in the East Midlands region of the UK.
June 21, 2024
Rankings by EY of the most attractive markets for renewable energy investment include battery storage, with US, China and UK as frontrunners.
June 20, 2024
NHOA Energy signed an agreement with Statkraft to supply a battery energy storage systems (BESS) for a 113MWh project in Coylton, Scotland.
June 19, 2024
A 25MW/55MWh battery energy storage system (BESS) has been commissioned by operator Renalfa IPP, using technology provided by Chinese firms Hithium and Kehua.

Most Popular

Email Newsletter