rPlus Energies submits Final License Application for 9GWh pumped hydro plant in Wyoming

LinkedIn
Twitter
Reddit
Facebook
Email

rPlus Energies has submitted a Final License Application for a 900MW/9GWh pumped hydro energy storage (PHES) plant in Wyoming, a milestone reached by only six projects in the past 20 years.

The Salt Lake-based firm’s subsidiary rPlus Hydro has submitted the Application with the Federal Energy Regulatory Commission (FERC), a move which kickstarts an environmental review and licensing process with local, state and federal bodies.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The Seminoe Pumped Storage project will have a maximum power output of 900MW and a discharge duration at that power of 10 hours, meaning a 9,000MWh/9GWh system.

Construction will cost around US$2.5 billion, the company said, and the project will become a crucial component of the regional transmission grid as more renewables come online.

Matthew Shapiro, rPlus Hydro CEO said: “Seminoe Pumped Storage will be an ideal match for Wyoming’s excellent wind energy resource, and will support Wyoming’s role as an energy leader. It can also help ensure efficient utilization of new transmission lines that are, or will soon be, under construction, such as the Gateway lines and TransWest Express.”

It was seven months ago that the company submitted a draft license application for the project.

Energy-Storage.news recently reported on one study which pegged the US’ potential for pumped hydro energy storage at 35TWh, equivalent to nearly another 4,000 projects the size of Seminoe. A map produced as part of that research showed the bulk of the identified sites are in the Mountain West region of the US where Wyoming is.

rPlus Hydro has other pumped hydro projects in the pipeline including Hurricane Cliffs, in Hurricane, Utah, which would contain a 166.6 MW reversible pump-turbine unit. The firm filed a application for a preliminary permit for that project in April 2022.

Energy-Storage.news’ publisher Solar Media will host the 5th Energy Storage Summit USA, 28-29 March 2023 in Austin, Texas. Featuring a packed programme of panels, presentations and fireside chats from industry leaders focusing on accelerating the market for energy storage across the country. For more information, go to the website.

Read Next

April 11, 2024
A Quinbrook Infrastructure Partners portfolio company will shortly begin construction on a 250MW/500MWh battery storage system in Queensland, Australia.
Premium
April 9, 2024
Battery technology startup Alsym Energy is keeping the exact chemistry of its product under wraps for the time being, the company has confirmed to Energy-Storage.news.
April 9, 2024
Developer and operator EsVolta has secured a US$185 million senior secured credit facility for its US battery energy storage system (BESS) project pipeline.
April 8, 2024
Investment manager Quinbrook Infrastructure Partners has closed funding for its Valley of Fire Fund, raising US$600 million in capital commitments from what it called “leading US and European institutional investors”.
April 8, 2024
US-based startups Torus and Alysm Energy have raised a combined US$145 million to scale up their non-lithium energy storage technology businesses.

Most Popular

Email Newsletter