Prologis Energy sells 400MW/800MWh BESS in Texas

LinkedIn
Twitter
Reddit
Facebook
Email

Real estate platform and energy storage investor Prologis Energy has sold a 400MW/800MWh battery energy storage system (BESS) located in Alvin, Texas, US.

Near Houston, Texas, the project is in one of the Electric Reliability Council of Texas’ (ERCOT’s) most congested zones.

Prologis secured the land, finalised an interconnection agreement, permitted the project, procured long-lead equipment and structured a 20-year ground lease and development services agreement.

The BESS is currently under construction, and Prologis expects 200MW to reach mechanical completion by the end of the year.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Prologis says the project will directly benefit customers of utility Centerpoint Energy.

Centerpoint Energy recently broke ground on a 160MW/320MWh BESS with developer SMT Energy near Prologis’ BESS.

ERCOT remains an incredibly popular market for BESS development, leading energy storage installations in Q4 2024.

A recent report from energy software and consulting group Ascend Analytics shows that ERCOT’s projected load growth over the remainder of the decade may be unachievable. Especially from data centre development, load growth in the state is becoming an increasing concern.

Ascend Analytics’ managing director of markets and strategy, Dr Brent Nelson, told Energy-Storage.news in an interview that the resultant increase in electricity scarcity and price volatility would be good for battery storage developer and investors’ revenue streams.

At the same time, both state and federal-level policies could have an adverse effect on building projects in the state.

Prologis, primarily known as a logistics real estate company, was founded in 1983. In 2007, the company began developing renewable energy projects as well.

In 2024, Prologis deployed its first BESS in Texas, in the city of Arlington. The project is co-located with a distribution centre also constructed by Prologis.

At that time, the company noted its intention to add nine more BESS projects to the state by the end of 2025.

Currently, the company claims to have over 8.5GW of grid-scale storage deployed and in development globally, with 47MW of storage capacity in the Americas.

Its other BESS projects, smaller scale than the most recently announced one near Houston, are located in Washington, Oregon, California, Arizona and New York.

8 September 2026
Barcelona, Spain
Battery & Energy Storage Tech Europe (BESTE) is Europe’s industrial scaling platform for stationary and industrial battery applications — not EVs. Taking place 8–9 September 2026 at Fira de Barcelona, BESTE brings together utilities, IPPs, energy-intensive industries, data centres, ports, rail, maritime, defence and aerospace OEMs — all deploying or integrating battery storage at scale. Over 100 companies already confirmed — including EDP Renewables, Acciona, Endesa, Naturgy, Neoen, Galp, Basquevolt and Veolia — alongside 40+ expert speakers and international institutional support from BEPA, BVES, LDES and Volta Foundation. Where Europe’s battery & ES ecosystem turns projects into reality.
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

July 19, 2026
Australian Prime Minister Anthony Albanese has said that large-scale data centres will be legally required to put at least as much energy into the grid as they draw from it, and that this supply must be renewable energy.
July 17, 2026
Battery energy storage systems (BESS) operating in California’s grid left approximately US$98 million on the table due to suboptimal bidding strategies, according to a new analysis from Gridmatic.
July 17, 2026
Zinc hybrid cathode battery and storage system maker Eos Energy Enterprises has announced a strategic partnership with the US Department of Defense (DoD) to “enhance the resilience of national defence infrastructure.”
July 17, 2026
The Port of Newcastle has become the first port in New South Wales, Australia, to be approved to safely store grid-scale lithium-ion battery storage systems.
July 16, 2026
Distributed energy resource (DER)-focused companies Sunrun and FranklinWH are expanding in California and Texas, US, respectively.