Powin Energy to supply Idaho’s first utility-scale storage project

LinkedIn
Twitter
Reddit
Facebook
Email

System integrator Powin Energy has been chosen by Idaho Power to supply 120MW/524MW of battery energy storage system (BESS) projects, the state’s first utility-scale storage developments.

The BESS projects are set to come online in summer 2023 and Idaho Power said they will help maintain reliable services during periods of high use, and help the utility achieve 100% clean energy by 2045. It still needs to be approved by the regulator and will likely comprise a 40MW and a 80MW system at separate locations.

The 40MW system may be at the Black Mesa solar facility in Elmore County, while the larger project could adjoin the Hemingway substation near the city Melba, although other sites are being considered for both.

“Battery storage enables us to use existing generation sources efficiently while setting the stage for more clean energy in the coming years,” said Adam Richins, Idaho Power senior vice president and chief operating officer.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Powin Energy will supply its Stack750 product, part of its Centipede platform, for the projects which will have an average duration of 4.36 hours. The modular BESS platform uses lithium iron phosphate (LF) battery cells from CATL and EVE with a cycle life of 7,300 and a DC round trip efficiency of 95% at four-plus hours, according to a datasheet from the Portland, Oregon-based firm.

Idaho Power submitted a request to the northwestern state’s Public Utilities Commission to determine whether the project proposal is in the public interest last week. It follows a request for proposals (RFP) in May last year for new resources coming online in 2023.

Powin’s press release said a strong economy and population growth are driving Idaho’s need for additional power capacity while transmission constraints have limited its ability to import energy from the Pacific Northwest and elsewhere. The state is seeking 1,700MW of energy storage and more than 2,100MW of solar and wind capacity by 2040, according to its latest integrated resource plan.

Powin Energy was the fifth-largest BESS system integrator in 2021 according to IHS Markit’s annual rankings report, after Fluence, NextEra Energy Resources, Tesla and Wartsila.

The company recently scored 5.8GW of BESS project orders from four developers in Taiwan and the US for a 2022-24 delivery timeframe and also recently entered the Indian market through a partnership. Executive VP Danny Lu contributed to a year-in-review article on Energy-storage.news in December.

8 September 2026
Barcelona, Spain
Battery & Energy Storage Tech Europe (BESTE) is Europe’s industrial scaling platform for stationary and industrial battery applications — not EVs. Taking place 8–9 September 2026 at Fira de Barcelona, BESTE brings together utilities, IPPs, energy-intensive industries, data centres, ports, rail, maritime, defence and aerospace OEMs — all deploying or integrating battery storage at scale. Over 100 companies already confirmed — including EDP Renewables, Acciona, Endesa, Naturgy, Neoen, Galp, Basquevolt and Veolia — alongside 40+ expert speakers and international institutional support from BEPA, BVES, LDES and Volta Foundation. Where Europe’s battery & ES ecosystem turns projects into reality.
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

August 26, 2026
DC-coupled solar-plus-storage projects can reduce the time needed for grid connection approval compared with AC-coupled designs.
Premium
August 25, 2026
Raafe Khan of Camelot Energy Group breaks down financial realities, market contradictions, and other dynamics shaping the energy storage space.
August 25, 2026
Shell has sold sonnen, the residential battery storage company it acquired in 2019, as the oil & gas major focuses its attention on “portfolio high-grading efforts.”
August 24, 2026
Scott Murtishaw, executive director at the California Energy Storage Alliance, discusses local opposition, safety misconceptions, and why the state’s containerised projects have proven safe.
August 24, 2026
GE Vernova and CATL selected for 1,216MWh Supernode Stage 3 in Queensland, which will expand Australia’s largest battery storage system.