Over 3GWh of BESS approved in UK in March

LinkedIn
Twitter
Reddit
Facebook
Email

The UK saw 1,590MW/3,179MWh of grid-scale BESS projects approved last month, bringing the total approved projects to around 55.4GW/117GWh.

That’s according to the latest data from Solar Media Market Research’s ‘Battery Storage: UK Pipeline & Completed Assets Database’ report.

The quantity of battery energy storage system (BESS) pipeline with planning consent is a roughly 5% increase on the 52.3GW/111.5GWh at the end of March, which itself was a roughly 5% increase on the 50.2GW/106.2GWh at the end of January, the data shows.

Major projects that were awarded planning consent last month include a 200MW/400MWh BESS from OnPath Energy and a 456MW project from Gresham House, both in Scotland, first reported by our colleagues at Solar Power Portal.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The milestone of planning consent could be crucial during regulator Ofgem’s reshuffle of the grid connection queue. January and February actually saw larger figures of BESS projects being approved, around 2,455MW/5,300MWh and 2,820MW/5,639MWh respectively.

The increase in operational capacity was comparatively lower in March than previous months, inching up around 1.7% to 6,374MW/9,043MWh from last month’s figure. The commissioning of Pulse Clean Energy’s 42MW/100MWh Hyde BESS, covered on Solar Power Portal, accounted for a big chunk of that increase.

The UK is Europe’s largest grid-scale BESS market, although Germany is larger overall if you include residential and commercial & industrial (C&I), as recent data from research firm LCP Delta and trade body EASE showed.

Our Market Research colleagues meanwhile estimate that around 700MW/1,400MWh of BESS projects started construction in the UK in the past month, meaning a total of around 18GWh is under construction.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.
2 December 2026
Italy
Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.

Read Next

October 19, 2026
Four-hour battery storage is less expensive than open-cycle gas turbines in the 43 markets in which both technologies were modelled, according to a new report from market research firm Wood Mackenzie.
October 16, 2026
A trio of large-scale 4-hour BESS projects in Germany have progressed towards construction, from Enertrag and Enlight, Vattenfall and Fluence, and Giga Storage.
October 15, 2026
Metals and energy group Metlen and conglomerate Karatzis Group have inaugurated the largest BESS in Greece, in a ceremony attended by the country’s Prime Minister.
October 15, 2026
ASL has set a target of 1,500MW of new firming infrastructure in NSW by the end of May 2033 and opened a consultation on the tender.
October 13, 2026
Bankability & offtake and regulatory & system reform were the key talking points on the opening panel of the Battery Asset Management Summit UK & Ireland 2026 which runs today and tomorrow (13-14 October).Â