Premium

Over 3GWh of BESS approved in UK in March

LinkedIn
Twitter
Reddit
Facebook
Email

The UK saw 1,590MW/3,179MWh of grid-scale BESS projects approved last month, bringing the total approved projects to around 55.4GW/117GWh.

That’s according to the latest data from Solar Media Market Research’s ‘Battery Storage: UK Pipeline & Completed Assets Database’ report.

The quantity of battery energy storage system (BESS) pipeline with planning consent is a roughly 5% increase on the 52.3GW/111.5GWh at the end of March, which itself was a roughly 5% increase on the 50.2GW/106.2GWh at the end of January, the data shows.

Major projects that were awarded planning consent last month include a 200MW/400MWh BESS from OnPath Energy and a 456MW project from Gresham House, both in Scotland, first reported by our colleagues at Solar Power Portal.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The milestone of planning consent could be crucial during regulator Ofgem’s reshuffle of the grid connection queue. January and February actually saw larger figures of BESS projects being approved, around 2,455MW/5,300MWh and 2,820MW/5,639MWh respectively.

The increase in operational capacity was comparatively lower in March than previous months, inching up around 1.7% to 6,374MW/9,043MWh from last month’s figure. The commissioning of Pulse Clean Energy’s 42MW/100MWh Hyde BESS, covered on Solar Power Portal, accounted for a big chunk of that increase.

The UK is Europe’s largest grid-scale BESS market, although Germany is larger overall if you include residential and commercial & industrial (C&I), as recent data from research firm LCP Delta and trade body EASE showed.

Our Market Research colleagues meanwhile estimate that around 700MW/1,400MWh of BESS projects started construction in the UK in the past month, meaning a total of around 18GWh is under construction.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.
3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.
2 December 2026
Italy
Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.

Read Next

October 5, 2026
Statkraft and Greenvolt Power have signed a 10-year tolling agreement covering 400MW of BESS across two operating projects in Poland.
October 2, 2026
Welcome to another edition of hot takes, snap analysis, gossip and of course, valuable insights from the LinkedIn feeds of energy storage and electricity insiders.
October 2, 2026
Elliot Squire, senior asset manager for Varco Energy, discusses current and future trends in battery storage.
October 2, 2026
Northland Power has closed financing on two large-scale battery energy storage system (BESS) projects in Poland.
October 2, 2026
Fu-Gen has sold a 100MW ready-to-build battery storage project in Finland to Nala Renewables, extending their Nordic BESS pipeline to 275MW.