UK reaches 6GW/8GWh of operational BESS; nearly 20GWh under construction

LinkedIn
Twitter
Reddit
Facebook
Email

Although last year saw a dip in installations and projects submitted for planning, the BESS market in the UK continues to steam ahead with over 8GWh online and nearly 20GWh being built.

That’s according to the latest data from Solar Media Market Research’s ‘Battery Storage: UK Pipeline & Completed Assets Database’ report.

A total of 120MW/140MWh of grid-scale battery energy storage system (BESS) capacity came online in January 2025, bringing the UK’s total operational capacity to around 6GW/8.3GWh.

Meanwhile, the amount that is now under construction has reached 8.2GW/18.7GWh. That means that, assuming no significant delays or cancellations, the UK’s BESS capacity should increase by at least 134% by GW power and 224% by GWh capacity in the next two or three years – to around 14.1GW/27GW.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

And that pipeline of projects with planning approval secured, on which investors can now make final investment decisions (FID) to then launch construction, is now over a staggering 100GWh of BESS.

The total that now has planning approval is approximately 50.2GW/106.2GWh of BESS, after 2,455MW/5,300MWh of projects received the green light over the course of January, including development consent orders (DCO) for Nationally Significant Infrastructure Projects (NSIPs).

Keen-eyed readers will note that this figure is very close to the sum total of two huge BESS projects for which developers announced planning consent last month, Fidra Energy’s Thorpe Marsh and Innova’s Almhome Energy Hub, together totalling 2,425MW/5,150MWh of capacity, covered by Energy-Storage.news.

However, Solar Media Market Research analysis found that Innova’s approval was actually granted by Doncaster council in October 2024, before being announced by Innova in January 2025, so it isn’t included in January’s data – though Thorpe Marsh’s 1.4GW/3GWh is.

Those projects should be exempt from an overhaul of the grid connections that the National Energy System Operator (NESO) and regulator Ofgem are currently working on, set to take place over the course of 2025.

Looking further ahead, the total pipeline of projects which are in the planning process after applications were submitted has now reached 27.7GW/56.6GWh, with 57MW/114MWh of project capacity submitted for planning permission in January. 874MW/1,747MWh of screening and scoping applications were submitted over the course of the month, a step which comes prior to a full planning application.

The Report’s data shows that 2024 actually saw a dip in installations and projects submitted for planning, outlined in a recent guest blog by Market Research analyst Charlotte Gisbourne.

Energy-Storage.news rounded up some of the projects which were announced as receiving planning consent and entering construction over January and December, some of which will be within these figures, last week.

2 December 2026
Italy
Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.
22 February 2027
InterContinental London - The O2, London, UK
The Future of Energy Storage Starts Here Three days in London where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into European storage, this is that room.

Read Next

Premium
November 5, 2026
We catch up with the CEO of Netherlands-headquartered system integrator Alfen to discuss its sodium-ion BESS partnership with CATL and plans for the technology in Europe.
November 5, 2026
Democrats scored major victories in the US Midterm elections, taking both the House and Senate and flipping several long-held Republican strongholds, with changes likely to occur in the clean energy sector.
November 3, 2026
Battery storage projects have won nearly 40% of the capacity in Belgium’s latest capacity market (CM) auction results, while Germany’s first has all gone to gas, paying nearly eight times more than Belgium in the process.
November 3, 2026
BW ESS has put its 350MW/1,240MWh Hams Hall BESS project in the UK into operation, the largest in Europe.
November 3, 2026
Revera Energy has doubled its holdco credit facility from US$150 million to US$300 million to fund its BESS pipeline in the UK and Australia.