Premium

NextEra, Brightnight and Cordelio seek gen-tie permits for 550MW of Arizona solar-plus-BESS

October 1, 2024
LinkedIn
Twitter
Reddit
Facebook
Email

Independent Power Producer (IPP) Brightnight is seeking approval from the Arizona Corporation Commission (ACC) for a Certificate of Environmental Capability (CEC) to construct a generation tie-in transmission line (gen-tie) in La Paz County, Arizona, to connect its Eagle Eye Solar and Storage Project to the local grid.

The application, filed 3 September 2024, was lodged with the Arizona Power Plant and Transmission Line Siting Committee by BNC DEVCO, LLC – a joint venture formed in 2018 between West Palm Beach Florida-headquartered Brightnight and Toronto, Ontario-based developer Cordelio Power.

The Brightnight and Cordilio JV is developing renewable energy projects throughout the US, including a 200MW/800MWh BESS in Washington known as the Greenwater Storage Project for which the pair have contracted with utility Puget Sound Energy, as reported by Energy-Storage.news last week.

Lithium or helium co-located 400MW BESS

The Eagle Eye project is a proposed 400MW solar development co-located with a 400MW BESS across 3,9000 acres of land administered by the Bureau of Land Management (BLM) located approximately 3 miles north of the Town of Wenden in La Paz County, Arizona.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The developer expects to utilise lithium-ion battery technology for the Eagle Eye project  from a “Tier-1 manufacturer” but is also considering using helium BESS technology according to documents filed with the BLM. Either way, the BESS will comply with the National Fire Protection Association 855 (NFPA 855), Standard for the Installation of Stationary Energy Storage Systems.

The project is expected to connect to the grid via Western Area Power Administration’s (WAPA’s) Harcuvar 230kV substation – for which the developer holds an interconnection queue position.

As well as an application with the ACC for the project’s grid connection infrastructure, the developer is also seeking federal approval of the solar and storage facility from the BLM through a Right-of-Way (ROW) application. Last week, the BLM issued a Notice of Segregation for the proposed Eagle Eye land, protecting it from mining for up to two years whilst the permitting process takes place.

The target in-service date for the project is December 2026.

NextEra: 150MW hybrid solar-plus-storage Selma Energy Center

Also occurring last week, Juno Beach, Florida-headquartered IPP NextEra Energy Energy Resources (NEER) filed a similar application with the ACC for the construction of a gen-tie line to connect its hybrid solar/storage Selma Energy Center to the grid.

The project, comprising 150MW of solar co-located with a 150MW lithium-ion BESS, is located west of the City of Coolidge in Pinal County, Arizona encompassing approximately 1,052 acres of land.

Interconnection to the grid will be via utility Salt River Project’s (SRP’s) Vah Ki 230kV substation.

NEER has already secured a Conditional Use Permit (CUP) from the City of Coolidge for a portion of the site, but still needs to obtain a non-major comprehensive plan amendment,

zone change, and Planned Area Development (PAD) from Pinal County.

The developer expects to invest US$389 million into the project which is expected online by December 2027.

‘Largest’ BESS in Arizona, and US$1 billion investment

Earlier this year, SRP and NEER announced that the Sonoran Energy Center was now operational, hailing it as the largest BESS in Arizona, as reported by Energy-Storage.news.

This is one of many NEER Arizona developments in Arizona, with others including a 450MW solar project paired with a 450MW BESS known as the Belmont Energy Center, located across 3,200 acres of land in Maricopa County.

The Belmont development will connect to Arizona Public Service’s (APS’) grid via the utility’s Delaney substation, as opposed to NEER’s Selma project which is also located in Arizona, but is expected to connect to the CAISO grid.

NEER expects to invest up to a US$1 billion into the Belmont project which is expected online as early as July 2026.

NEER’s impact can be felt across large portions of North America, with the IPP claiming to have some form of presence across 49 US states and four Canadian provinces.

The developer is planning some of the continent’s largest BESS projects, including its 600MW Roadhouse Energy Storage project located in the City of Ontario, California.

For further details on the development, including information relating to the project’s offtake agreement with a public utility, see this recent premium article from Energy-Storage.news.

Read Next

March 6, 2026
Thailand is increasing its renewable generation but its energy storage market still lags behind, while there is support for the upstream industry, writes analyst Charlotte Gisbourne.
March 5, 2026
Developer Avantus has closed a financing package of over US$300 million for the 100MWac/130MWdc solar, 400MWh BESS Kitt Solar and Energy Storage Project in Pinal County, Arizona, US.
March 5, 2026
Large-scale BESS deployments in Romania are benefiting from country-specific drivers, helping Romania emerge as a busy grid-scale market.
Premium
March 5, 2026
In this second part of our interview with Wood Mackenzie energy storage analysts, we look at risk factors and mitigation across the European and US markets.
March 5, 2026
Jeff Monday of Fluence believes Australia can transform its data centre boom from a grid constraint into a growth opportunity using BESS.