Younicos commissions 1MW / 2MWh battery that enables both C&I and utility use cases in Denver

LinkedIn
Twitter
Reddit
Facebook
Email
Younicos’ Y.Cube units are put into place at Peña Station NEXT, Denver, Colorado. Image: Younicos.

Work has been completed on a 1MW / 2MWh battery energy storage system for a ‘multi-resource microgrid’ in Denver, by Younicos and its project partners, Panasonic and utility Xcel Energy.

Younicos said earlier this week that the lithium-ion battery storage system which the company’s CEO described as having a “hybrid utility-C&I (commercial & industrial) use case,” has been commissioned.

The system is being used to optimise the use of 1.6MW of carport PV and 259kW of rooftop PV at the Peña Station NEXT, a sustainable development in Denver, Colorado. In a statement, Younicos CEO Stephen L Prince said the project will provide “energy security, resiliency, and financial returns from stacked grid services”. The project’s energy storage is connected to Xcel Energy’s transmission feeder lines.

“The collaboration with Panasonic on this microgrid project has been seamless and productive, resulting in a state-of-the-art microgrid that will anchor this development,” Prince said.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

As originally announced in November, the installation uses four of Younicos’ own Y.Cube plug-and-play energy storage hardware units, which includes power conversion system and DC battery block. In addition to allowing for better integration of the PV, it will provide services including peak demand reduction – a C&I use case – and frequency regulation, a front-of-meter ancillary grid service. It also performs energy arbitrage tasks, charging the battery when prices are low and discharging when prices are high in response to automated price signals. In all the battery system is used for five stacked use cases.

The microgrid system’s load is ‘anchored’ at a Panasonic operations hub building onsite which has a built-in intelligent energy management system. Panasonic’s subsidiary Pansonic CityNOW is developing many of the Peña Station NEXT facilities.

In addition to being a manufacturer of many energy and clean tech products from solar panels to its own lithium-ion batteries (including in conjunction with Tesla at the Gigafactory) the Japanese company is known in its home country for developing Fujisawa Smart Town, a sustainable housing development consisting of smart homes that combine energy efficiency, solar PV and batteries. Panasonic’s work on Peña Station NEXT is set to build on lessons learned from that project.

Panasonic, Younicos and Excel Energy have produced a whitepaper on the Peña Station NEXT project which can be downloaded here.

Aerial view of the development with 1.6MW carport PV in distance. Image: Younicos.

Read Next

Premium
July 23, 2026
ESN Premium speaks with Bryen Alperin and Sophie Brkovic of Foss & Company about the tax equity investor’s entrance into microgrids.
July 23, 2026
Spain has awarded €165 million to seven pumped hydro storage projects totalling around 2.1GW/21GWh, while Portugal has set a target of 1.4GW of new pumped hydro capacity by 2040.
Sponsored
July 22, 2026
We caught up with Michael Koller, Solutions Director for Europe and the UK with Envision Energy, at this year’s Smarter E Europe trade show in Munich. 
Sponsored
July 14, 2026
Huawei FusionSolar’s new Smart String Grid-Forming ESS Platform, LUTERRA, is born from technology breakthroughs designed to drive customer success.
July 13, 2026
Update 16 July 2026: Energy Storage Europe sent a statement to Energy-Storage.news on the leaked plan.