UK’s ancillary services dispatched by web-based platform for first time

July 25, 2018
LinkedIn
Twitter
Reddit
Facebook
Email
Image: Zenobe Energy.

UK transmission network operator (TNO) National Grid has used a new web-based platform to dispatch ancillary services using battery storage in the first example of the new system being implemented across its reserve products.

First revealed in December 2017 as part of the transmission system operator’s Product Roadmap For Frequency Response and Reserve, the Ancillary Services Dispatch Platform (ASDP) is intended to allow National Grid greater access to new technology types, enhancing flexibility across energy sources.

It was used on 19 July to procure stored power from Zenobe Energy, which supplied 24MWh over a 30 minute period from a 50MW facility.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

24MWh of stored power from Zenobe Energy was dispatched over a 30 minute period last week. Image: Zenobe Energy.

Zenobe Energy, which counts former National Grid chief executive Steve Holliday as its non-executive chairman, was until recently known as Battery Energy Storage Solutions (BESS). It is not known how the company was selected to take part in the dispatch pilot, as Zenobe did not respond to requests for clarification from our sister site Current±. Under its former name, the company boasted of netting more than US$100 million in outside investment between November 2017 and January of this year.

However, it would have utilised some of its 63MW portfolio of battery sites to deliver the total dispatched volume. The firm’s sites include the 29MW site at Aylesford in Kent and the 20MW site at Claredown in Essex, as well as the 9.6MW Kings Barn battery in West Sussex.

It also counts five battery sites co-located with solar farms within its list of assets, adding a further 3.85MW to battery storage capacity.

While National Grid would not comment further, it is expected to continue to utilise the ASDP following the successful dispatch of services using battery storage.

It will be used to aggregate and summarise the reserve volumes available to the control room, coordinate despatch across a large number of connected assets and providers, and provide a route for automated monitoring of delivery.

In December, the grid operator said it would roll the platform out further into the Short Term Operating Reserve (STOR) market, with the ambition to replace the existing despatch system with ‘a flexible, scalable and secure platform’.

Read Next

January 21, 2026
The UK market saw strong interest and activity in 2025 but now appears to be shifting from a development market to one focused on execution, writes Solar Media analyst Charlotte Gisbourne.
January 21, 2026
Another roundup of European grid-scale BESS project news, led by MORE and Zenobe putting Greece and UK projects into operation, and major project financings/construction starts by Acacia in France, Greenvolt in Hungary and Eco Stor in Germany.
January 21, 2026
Luke Witmer, VP of software engineering at Wärtsilä Energy Storage, explains why 2025 was an “awkward” year, but one that saw the industry grow taller than ever.
January 20, 2026
While the UK grid-scale BESS market continues to be among the busiest in Europe, there are still huge questions and plenty work to be done in several key policy areas.
January 20, 2026
Global infrastructure investor I Squared Capital has launched ANZA Power, a next-generation independent power producer (IPP) in Australia and New Zealand.