UK transmission network operator (TNO) National Grid has used a new web-based platform to dispatch ancillary services using battery storage in the first example of the new system being implemented across its reserve products.

First revealed in December 2017 as part of the transmission system operator’s Product Roadmap For Frequency Response and Reserve, the Ancillary Services Dispatch Platform (ASDP) is intended to allow National Grid greater access to new technology types, enhancing flexibility across energy sources.

It was used on 19 July to procure stored power from Zenobe Energy, which supplied 24MWh over a 30 minute period from a 50MW facility.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

24MWh of stored power from Zenobe Energy was dispatched over a 30 minute period last week. Image: Zenobe Energy.

Zenobe Energy, which counts former National Grid chief executive Steve Holliday as its non-executive chairman, was until recently known as Battery Energy Storage Solutions (BESS). It is not known how the company was selected to take part in the dispatch pilot, as Zenobe did not respond to requests for clarification from our sister site Current±. Under its former name, the company boasted of netting more than US$100 million in outside investment between November 2017 and January of this year.

However, it would have utilised some of its 63MW portfolio of battery sites to deliver the total dispatched volume. The firm’s sites include the 29MW site at Aylesford in Kent and the 20MW site at Claredown in Essex, as well as the 9.6MW Kings Barn battery in West Sussex.

It also counts five battery sites co-located with solar farms within its list of assets, adding a further 3.85MW to battery storage capacity.

While National Grid would not comment further, it is expected to continue to utilise the ASDP following the successful dispatch of services using battery storage.

It will be used to aggregate and summarise the reserve volumes available to the control room, coordinate despatch across a large number of connected assets and providers, and provide a route for automated monitoring of delivery.

In December, the grid operator said it would roll the platform out further into the Short Term Operating Reserve (STOR) market, with the ambition to replace the existing despatch system with ‘a flexible, scalable and secure platform’.

Read Next

December 3, 2025
Energy-Storage.news proudly presents our sponsored webinar with Trina Storage, ‘Powering Certainty: Bankable Energy Storage, with Elementa 2 Pro’.
December 2, 2025
Manoa Energy and HD Renewable Energy Japan have begun commercial operation of a 50MW/104MWh battery storage project in Hokkaido, Japan.
December 1, 2025
European BESS news from project owners Premier Energy Group, Verbund, Eco Stor, Ingrid Capacity, Ric Energy, Ganfeng Lithium, EP Group, RWE and Giga Storage, securing acquisitions, financings and route-to-market (RTM) deals for multiple gigawatts of capacity this past week.
November 30, 2025
Ampyr Australia has secured a 15-year battery storage agreement with InCommodities for the 600MWh Bulabul BESS in New South Wales.
November 27, 2025
The Western Australian government has launched the first stage of an Expression of Interest (EOI) process for a 50MW/500MWh vanadium flow battery energy storage system (VBESS) in Kalgoorlie.