UK investor claims 30% fall in battery costs still needed for projects to become viable

LinkedIn
Twitter
Reddit
Facebook
Email
Katherine Vinnicombe of Foresight Group (far right) on the panel at the Renewable Futures event this week. Image: Regen / Twitter.

Battery storage technology costs will have to fall by a further 30% before projects in the UK are feasible without lucrative frequency response revenues, a leading investor has said.

Speaking during yesterday’s Renewable Futures event organised by Regen, a non-profit consultancy for low carbon energy, Katherine Vinnicombe, investment manager at Foresight Group, made the remark amidst a discussion centring around potential disruptors in the UK's energy market.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

Foresight has been one of the early investors in UK battery storage assets, buying up two projects backed by Enhanced Frequency Response (EFR) contracts.

Those four-year deals, Vinnicombe said, are responsible for around 70% of the projects’ development cost and, as a result, the investor believes the merchant risk of recouping the remaining 30% from alternative revenue streams like arbitrage is palatable.

But the same cannot be said for projects without access to similar frequency response revenues, a market that is already showing signs of saturation.

With National Grid expecting to require around 400MW of frequency response services – half of which is already contracted out under the EFR deals – just 200MW of contracts will be up for grabs under other frequency response markets. With a large number of battery storage projects aiming to come on stream, Vinnicombe said she expects such saturation to send contract prices tumbling. Head of business development at National Grid Claire Spedding recently said developers should not rely too heavily on income streams for grid services, with particular reference to two-year contracts for firm frequency response (FFR).

Reducing or entirely removing revenues from frequency response would cause standalone battery storage projects to source revenues entirely from arbitrage and access to the balancing mechanism, and technology costs will have to fall in line with those revenues in order for projects to economically viable.

Co-located projects could provide a minor stopgap for developers however. Rather than technology costs falling, retrofitting batteries onto generators with pre-existing grid connections and associated infrastructure could achieve similar cost reductions to bring the entire project cost down to manageable levels.

Co-located projects require ‘specific circumstances’ to be economical

One UK company, Anesco, has been a keen developer of co-located storage, retrofitting 10 batteries on existing solar farms and utilising similar designs to deploy Clay Hill, the UK’s first subsidy-free solar farm. Vattenfall are too co-locating solar and onshore wind and a raft of other developers are investigating similar.

Vinnicombe said these projects could represent the “next wave” of storage assets connecting to the grid in the UK, but these would require very specific circumstances to be economical – in much the same way Clay Hill did – and meaningful development would have to wait for technology costs to fall.

She did however suggest that further opportunities lie in behind the meter storage applications that enable intensive users of energy to peak shave, and also backed PPA (power purchase agreement) providers and aggregators to bring other interesting revenue models to the market which could make projects palatable. 

Read Next

May 1, 2025
Copenhagen Infrastructure Partners (CIP) will divest a 50% ownership stake in its 500MW Coalburn 1 BESS to alternative investor AXA IM Alts.
Sponsored
May 1, 2025
Alper Peker and Dominic Multerer of Camopo explain how flexibility is the key to long-term profitability for hybrid renewables-plus-storage power plants.
May 1, 2025
Yarra Energy Foundation has secured funding to install three new community batteries in and around Melbourne, Victoria, Australia.
May 1, 2025
AEMO has revealed that, as of March 2025, the pipeline of new standalone BESS in the NEM has increased by 86% year-on-year (YoY).
April 29, 2025
Energy-Storage.news proudly presents our sponsored webinar with Clean Horizon on the economics of renewables-plus-storage in Europe.

Most Popular

Email Newsletter