A smart grid pilot will be put into action in the Thai province of Mae Hong Son, to integrate and balance growing shares of renewable energy using battery energy storage systems (BESS).

The Electricity Generating Authority of Thailand (EGAT) and the country’s Provincial Electricity Authority (PEA) have signed an agreement to investigate the use of batteries under the country’s Smart Grid Master Plan, a five-year development plan signed off in 2016.

An expert team from Chulalongkorn University found in a recent study that Mae Hong Son, a remote and mountainous province in northern Thailand lacking in existing large-scale power plants is a suitable area for using smart grid technology to enhance local generation and distribution of electricity.

At present, the region gets its power through PEA transmission lines, through hydro and solar power and a diesel power plant. Outages are frequent and the two partners will investigate how the reliability of local energy supply can be improved, in a project aimed at sharing information and studying the management of power supply.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Under the terms of a Memorandum of Understanding (MOU) signed by EGAT and PEA shortly before the end of October, a working study group will be set up to study four aspects of battery and renewables integration:

  • BESS will be connected to PEA’s Mae Hong Son distribution system according to engineering standards and grid codes. It will also be operated and evaluated in ‘islanded’ mode, running independently of the local grid.
  • Protocols will be implemented on the Mae Hong Son network to support that latter transition from grid-connected to islanded modes.
  • The exchange of relevant data which is likely to include communications and connection point protocols as well as the application of data to improve working processes.
  • Testing and controlling the smart grid system, including in grid-connected and islanded modes and from there figuring out and mapping how such systems could be suitable for deployment in the local area.

The smart grid will be controlled by an EGAT-designed controls system. The announcement comes just under a year after EGAT announced battery energy storage to be a “new dimension” for the management of electricity. Thailand has around 1,031MW of pumped hydro storage already, and is apparently planning to deploy a further 2,100MW. EGAT identified however that batteries can be deployed more quickly and taking up far less space, while offering fast response times and other advantages in the way it can be controlled and used for a variety of applications.

In a November 2017 release, EGAT referred to three battery storage systems either already deployed or planned for its networks, mostly in areas where generation and transmission equipment is located, including one 3MW project in Mae Hong Son with 15 minutes duration of storage. At that time, EGAT said the 3MW system. EGAT also said last year that it is proposing that the majority of its BESS deployments will be in southeastern Thailand where there are large amounts of renewable energy generation assets.

Read Next

January 7, 2026
On 19 December, a fire occurred at energy storage developer Convergent Energy & Power’s Church Street Battery Storage Facility in Warwick, New York, US.
January 6, 2026
The Australian Energy Regulator (AER) has confirmed that 244 community battery energy storage systems (BESS) are now connected to the country’s distribution networks.
January 6, 2026
Technology provider Dalian Rongke Power (Rongke Power) and infrastructure developer China Three Gorges Corporation (CTG) have brought online the world’s first gigawatt-hour-scale flow battery energy storage project.
January 6, 2026
In this blog, Kashish Shah, market development manager at Wärtsilä Energy Storage, argues that Australia’s complex battery storage market makes full-scope integration the most viable path for successful project delivery.
January 6, 2026
Atmos Renewables and Potentia Energy have secured financing packages for their Australian renewables and energy storage portfolios.