PPA signed for Middle East’s ‘largest’ solar-plus-storage project

LinkedIn
Twitter
Reddit
Facebook
Email
The signing was overseen by minister of energy and mineral resources Saleh Al Kharabsha. Image credit: Philadelphia Solar.

The power purchase agreement (PPA) for what is claimed to be the Middle East’s largest solar-plus-storage project has been signed.

Jordanian PV manufacturer and EPC Philadelphia Solar is developing the 11MW generation site, which will be paired with a 12MWh lithium-ion battery. The system will perform peak shaving and load shifting duties to support the grid during daytime hours.

The Irbid District Electricity Company has signed a 20-year PPA for power from the site. The signing was overseen by minister of energy and mineral resources Saleh Al Kharabsha.

Philadelphia Solar will install its own 320Wp polycrystalline modules and its own single-axis tracker for the project. Further details on the energy storage system were not provided and Philadelphia Solar was not available for further comment.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Jordan is energy-poor and relies heavily on fossil fuel imports from neighbouring countries. Historically, diesel and fuel oil have been the dominant sources of electricity but recent renewable energy tenders have helped to decrease this dependence.

Read Next

August 17, 2026
A new report from climate consultancy Ember highlights the important relationship between energy storage and solar, unlocking the “era of anytime solar.”
August 17, 2026
Independent power producer (IPP) Econergy has signed financing agreements for its Părău 2 solar and energy storage project in Brașov County, Romania.
August 13, 2026
Denmark-headquartered investor Copenhagen Infrastructure Partners (CIP) has brought its 500MW, 2-hour duration Coalburn 1 battery energy storage system (BESS) into commercial operation.
August 12, 2026
Spanish renewables developer Acciona Energía has unveiled plans to install two battery energy storage systems (BESS).
August 12, 2026
Ahead of the Battery Asset Management Summit Australia 2026, we take a look at some of the key debates set to take centre stage at the event.