Wind turbines at the site, which is thought to be the first Australian mine to use wind power. Image: EDL.

A lithium-ion battery energy storage system (BESS) supplied by French manufacturer and system integrator Saft has enabled a gold mine in Australia to meet more than 50% of its energy demand with renewable energy.

Power station operating company EDL has implemented what is already thought to be Australia’s biggest microgrid operating on hybrid renewable sources – combining wind and solar – along with gas / diesel engines for backup. The system has a combined capacity of 56MW including 13MW of battery storage and is at Agnew Gold Mine, Western Australia, owned and operated by mining company Gold Fields.

Gold Fields contracted EDL to provide the 600 square kilometre mine site’s power solution through a 10-year agreement. While it allows the site to run on 50% renewables on average, at times it can deliver up to 85% of the site’s power requirements with wind and solar, EDL chief executive James Harman said. The project was completed in May. About 10% of its total cost of around AU$110 million (US$80 million) was funded through a grant from the government-backed Australian Renewable Energy Agency (ARENA).

The 13MW / 4MWh battery storage system, based on six containerised Saft Intensium Max+ 20M megawatt-scale battery storage units allows EDL’s microgrid to integrate variable renewable energy including 4MW of solar and 18MW of wind while maintaining power quality. It is also thought to be the first Australian mine microgrid to incorporate wind power. It also uses a 21MW thermal power engine.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Housed in 20ft containers, the Intensium Max lithium-ion battery systems sit alongside three containers twice as long that house its power conversion system (PCS), transform and MV switchgear. In addition to maintaining the power quality to the mine as it feeds in renewable power from variable sources the battery system will also provide spinning reserves to maintain the microgrid’s stability, minimising the need for idling fossil fuel generators to stay running.

Saft said in a press release that the battery storage, fitted out and tested at the company’s Jacksonville, Florida manufacturing hub, is designed to withstand the difficult desert conditions at the site, including temperatures which can reach 48 degrees Centigrade (118.4 Fahrenheit).

Mines have been seen as a low-hanging fruit opportunity for solar, wind and battery hybrid microgrids, given the fairly intensive energy demands of sites are often coupled with them being a long distance from reliable grid power. This means that, like islands, polluting and expensive fossil fuels need to be transported in, again, often over long distances. In February, Rio Tinto said it will tender for 34MW of solar and 12MWh of storage solutions for one of its mining sites, also in Western Australia, while 17MW / 15MWh of battery energy storage is being built alongside a 30MW solar PV plant at a gold mine in Mali, Africa, to give just two recent examples.

Battery storage systems in the foreground and solar panels behind them at the Agnew Gold Mine. Image: EDL.

Read Next

April 17, 2026
Synergy has submitted a hybrid renewable energy project to Australia’s EPBC Act, featuring a 500MW battery energy storage system (BESS).
April 16, 2026
Neoen Australia has referred its 3,200MWh Bondo wind-plus-storage project for federal environmental assessment.
April 16, 2026
Amazon has announced nine new renewable energy PPAs in Australia totalling 430MW of capacity, eight of which include co-located BESS.
April 16, 2026
Alinta Energy has commenced main construction works on its 1,000MWh Stage 1 of its Reeves Plains BESS in South Australia.
Premium
April 15, 2026
Fluence’s chief growth officer, Jeff Monday, and Australia strategy lead, Sam Markham, discuss hyperscale opportunities, grid-forming evolution, and the company’s high-density Smartstack deployment plans.