Around 200GW of energy storage in US interconnection queues at end of 2020

LinkedIn
Twitter
Reddit
Facebook
Email
A solar-plus-storage installation in North Carolina. More than one-third of the solar in the interconnection queues is proposed as a hybrid plant. Image: Lockheed Martin.

A record amount of solar capacity and energy storage is currently in US transmission interconnection queues, according to a new study from Lawrence Berkeley National Laboratory (Berkeley Lab).

At 462GW, solar accounts for most of the total generator capacity in the queues, which reached a record of more than 755GW and an estimated 200GW of storage capacity at the end of 2020. To put that in perspective, the US had 1,117GW of utility-scale electricity generating capacity in operation last year.

Proposed large-scale electric generation and storage projects must apply for interconnection to the bulk power system via interconnection queues. Berkeley Lab said that while many projects that apply for interconnection are not subsequently built, data from the queues provide a general indicator for mid-term trends in developer interest.

To read the full story, visit PV Tech.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

20 April 2027
Renaissance Dallas at Plano Legacy West Hotel, Dallas, Texas, Dallas
Policy, Procurement and Power Demand: Defining the Next Chapter for Energy Storage. Two days in Dallas where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into US storage, this is that room.

Read Next

November 11, 2026
Excelsior Energy Capital-backed developer Lydian Energy has brought its 150MW/600MWh Faraday battery energy storage system (BESS) project in Utah County, Utah, US into commercial operation.
November 11, 2026
Calibrant Energy, an energy-as-a-service platform, has closed a US$145 million debt facility for solar and energy storage projects across several US power markets.
Premium
November 10, 2026
The energy storage industry is abuzz with discussion of passing BAAJA following Democrats’ taking of the House and Senate in the 2026 US midterm elections.
November 9, 2026
A new report prepared by The Brattle Group for The Pew Charitable Trusts finds that removing barriers to distributed energy resources (DERs) could avoid an estimated US$614 billion in US power system costs through 2050.
November 9, 2026
Derrick Flakoll, senior policy associate for North America at BloombergNEF, has offered a more measured take on how the Democrats’ midterm victories could affect the battery energy storage system (BESS) sector.