Around 200GW of energy storage in US interconnection queues at end of 2020

May 28, 2021
LinkedIn
Twitter
Reddit
Facebook
Email
A solar-plus-storage installation in North Carolina. More than one-third of the solar in the interconnection queues is proposed as a hybrid plant. Image: Lockheed Martin.

A record amount of solar capacity and energy storage is currently in US transmission interconnection queues, according to a new study from Lawrence Berkeley National Laboratory (Berkeley Lab).

At 462GW, solar accounts for most of the total generator capacity in the queues, which reached a record of more than 755GW and an estimated 200GW of storage capacity at the end of 2020. To put that in perspective, the US had 1,117GW of utility-scale electricity generating capacity in operation last year.

Proposed large-scale electric generation and storage projects must apply for interconnection to the bulk power system via interconnection queues. Berkeley Lab said that while many projects that apply for interconnection are not subsequently built, data from the queues provide a general indicator for mid-term trends in developer interest.

To read the full story, visit PV Tech.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

24 March 2026
Dallas, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2026!

Read Next

December 5, 2025
Developer BrightNight and independent power producer (IPP) Cordelio Power have announced financial close of the 200MW/800MWh Greenwater battery energy storage system (BESS) in Washington state, US.
December 4, 2025
RWE Clean Energy has commissioned the Stoneridge Solar PV project in Texas, adding 200MW of solar PV and 100MW/200MWh BESS to its operational portfolio.
Premium
December 4, 2025
A subsidiary of utility Northern Indiana Public Service Company (NIPSCO) has struck a deal with Amazon to construct 3GW of new dispatchable capacity, with the aim of serving the tech company’s planned data center expansion.
December 4, 2025
PJM has awarded 23 battery energy storage system (BESS) resources, totalling 2.2GW, with interconnection agreements (IAs) in its first transition cycle (TC1) of the reformed interconnection process.
December 2, 2025
South Carolina public utility company Santee Cooper has applied for a Certificate of Environmental Compatibility and Public Convenience and Neccessity (CECPCN) with the state’s public service commission (PSC), for its 300MW/1,200MWh battery energy storage system (BESS).