National Grid’s UK frequency response procurement process aims at transparency, simplicity

December 20, 2017
LinkedIn
Twitter
Reddit
Facebook
Email
Image: Vattenfall.

National Grid has revealed a simplified, more standardised approach to Firm Frequency Response (FFR) procurement whilst teasing the first details of its fast-response follow-up to EFR.

The UK’s system operator has today published its ‘Product Roadmap for Frequency Response and Reserve’ document, a response to this year’s System Needs and Product Strategy (SNAPS) document that outlines certain decisions it has made over how FFR tenders will be carried out in the future.

It follows a three-stage approach to modernisation of National Grid’s frequency response market. Stage one, or rationalisation, was completed at the beginning of November when sweeping changes to grid balancing markets were confirmed.

This second stage, earmarked for simplification of current processes, mainly surrounds how providers tender for capacity, with the status quo considered too complex and suffering from a lack of transparency.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Currently, providers can tender in for any number of months from one to a total of 24 months, making it difficult for National Grid and other parties to compare results between months.

National Grid is now changing this to allow operators to tender for more standardised periods, namely the front month and the front quarter of that particular auction, as well as pre-determined seasons extending out to 30 months in the future, as detailed below.

These changes, the system operator has said, will drastically simplify future auctions and allow it to gather more information for post-tender reports.

Meanwhile National Grid is to also address complaints surrounding the complexity of contracts – which many respondents to the System Needs and Procurement document bemoaned – by simplifying the contracts in particular.

More detail on the short-term actions to improve FFR will be made available in Q1 2018, with simplified contracts made available for participants in the following quarter. Testing and compliance is pencilled in for Q3.

National Grid has also outlined its intent to secure faster-acting response in a similar frame to the EFR product, capable of responding to sudden frequency fluctuations caused by plant loss. It has separated this into dynamic containment of 60 seconds and static containment of as much as 30 minutes.

The SO had previously guided that a replacement for EFR, which procured 200MW of capacity from battery storage projects last year, would be revealed as early as March 2018. This is now being pushed “towards the back end of 2018”, with National Grid eager for more time to better harmonise the faster-acting product with existing FFR tenders and consider specific details such as tender volume.

Read Next

January 21, 2026
The UK market saw strong interest and activity in 2025 but now appears to be shifting from a development market to one focused on execution, writes Solar Media analyst Charlotte Gisbourne.
January 21, 2026
Another roundup of European grid-scale BESS project news, led by MORE and Zenobe putting Greece and UK projects into operation, and major project financings/construction starts by Acacia in France, Greenvolt in Hungary and Eco Stor in Germany.
January 20, 2026
While the UK grid-scale BESS market continues to be among the busiest in Europe, there are still huge questions and plenty work to be done in several key policy areas.
Premium
January 19, 2026
US-based iron-sodium battery manufacturer Inlyte Energy has successfully completed a factory acceptance test of its first field-ready battery at its facility near Derby, UK, witnessed by representatives from US utility Southern Company.
January 13, 2026
Another busy week of large-scale BESS project news across Europe, led by CountourGlobal putting a 202MW/505MWh BESS into commercial operation in Bulgaria.