Hungary’s first city-owned smart grid project to feature 1.2MW / 2.4MWh of battery storage

August 27, 2020
LinkedIn
Twitter
Reddit
Facebook
Email
Two Convert SC Flex converters will be used for the project. Image: AEG Power Solutions.

Hungary’s first “city-owned smart grid project” will be powered by a 1.3MWp PV facility and supported by a 1.2MW lithium-ion battery energy storage system with a capacity of 2.4MWh.

AEG Power Solutions contacted Energy-Storage.news to announce its involvement in the project and said that its Convert SC Flex storage converters have been chosen for the smart grid, which will power sports facilities in the Hungarian city of Békéscsaba with green energy.

The battery system, built up on 7.61kWh modules in a fire protection rack, will be connected to the grid through two Convert SC Flex converters with a power rating of 600kVA each. AEG will also provide 650kVa inverters to connect to the DC output of solar panels.

AEG said the storage converters offer grid fault detection and islanding as well as resynchronisation once the supply is provided by the public grid again. In the event of any grid failure, the systems switch to off-grid operation and supply electricity directly from the solar plant and energy storage to the sports facilities. As a result, they will be able to continue to operate even in the event of a grid power outage.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Andreas Becker, head of grid and storage at AEG Power Solutions, said the project represents a “great opportunity” to prove the “unique off-grid features” of the Convert SC Flex in the field.

Under development by local partner INFOWARE, which is also providing energy management system (EMS) solutions to the smart grid, it is expected the project will be complete by the end of 2020.

Image: AEG.

Read Next

February 10, 2026
Energy infrastructure platform Revera Energy has completed an expanded US$150 million credit facility to accelerate development and construction of its battery storage, solar, and green hydrogen project pipeline across Australia and the UK.
February 8, 2026
Sam Markham of Fluence Australia believes grid-forming BESS are essential to deliver a safe, secure and affordable decarbonised power system.
February 6, 2026
Iberdrola Australia has officially opened its 65MW/130MWh Smithfield BESS in western Sydney, New South Wales, ahead of schedule.
February 5, 2026
Valent Energy has received development approval from the New South Wales government and satisfied AEMO grid compliance requirements under clause 5.3.4a for its 150MW/437MWh Armidale Battery Energy Storage System (BESS).
February 5, 2026
Octopus Australia has announced plans to develop what it claims is Australia’s “largest planned battery energy storage system (BESS)” in New South Wales.