Hawaii’s main utility Hawaiian Electric has entered into contract negotiations with the developers of 15 renewable energy projects, including solar, wind and a combined 2.1GWh of energy storage.

The projects are spread across the islands of Oahu, Hawaii Island and Maui and will combine renewable energy generation including biofuel-powered generators and energy storage to ensure firm generation.

The contacts entered into after negotiations are expected to cover around 517MW of variable generation, 654MW of firm generation and 2.1GWh of energy storage, with completion dates mandated for between 2026 and 2033.

Developers include Ameresco, Clearway – both having worked on co-located projects in Hawaii previously – Longroad Development, AES and Pacific Current and Terraform, which added a storage facility to a small wind farm there a few years ago. AES is the US-listed energy firm with a global presence, one of the founding companies of battery energy storage integrator Fluence.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Seven will be on the island of Oahu, four on Hawaii Island and four on Maui, totalling 990MWh, 320MWh and 834MWh of energy storage capacity respectively. See a full table of the projects below.

Project nameIslandDeveloperTechnologySize
Puuloa EnergyOahuAmerescoInternal combustion engines (biofuel)99MW
Puuloa SolarOahuAmerescoSolar + BESS6MW + BESS
Base ProposalOahuKalaeloa Partners LPCombustion turbine (biofuel)208MW
Waiau RepowerOahuHawaiian ElectricCombustion turbine (biofuel)253MW
Mahi Solar and StorageOahuLongroad DevelopmentSolar + BESS120MW + BESS
Makana LaOahuClearway Energy GroupSolar + BESS80MW + BESS
Par Hawaii Renewable Combined Heat & PowerOahuPar Hawaii RefiningCombined heat & power (biofuel)33.9MW
Kuihelani Phase 2 SolarMauiAES Corp.Solar + BESS40MW + BESS
Puu Hao SolarMauiAES Corp.Solar + BESS20MW + BESS
Kaheawa Wind 1MauiTerraform USWind30MW
Pulehu Solar & StorageMauiLongroad EnergySolar + BESS20MW + BESS
Keamuku SolarHawaii IslandAES Corp.Solar + BESS86MW + BESS
Puako SolarHawaii IslandClearway Energy GroupSolar + BESS60MW + BESS
Kaiwiki SolarHawaii IslandClearway Energy GroupSolar + BESS55MW + BESS
Hamakua Firm Renewable EnergyHawaii IslandPacific CurrentCombined Cycle (biofuel) + BESS60MW + BESS

“These projects will help move Hawaii closer to its clean energy goals, while adding critical grid reliability with firm renewable energy,” said Rebecca Dayhuff Matsushima, vice-president of Resource Procurement for Hawaiian Electric. “Adding energy storage and generation from firm renewables to our portfolio will make it easier for Hawaiian Electric to retire older, less flexible fossil fuel-fired plants.”

The two combustion engine projects on Oahu and the Hamakua project on Hawaii Island are transforming facilities that currently burn imported fossil fuels into biofuel-based ones.

Once the contracts between Hawaiian Electric and the project finalised they will be submitted to the Public Utilities Commission of Hawaii for review and approval.

The projects need to contribute US$3,000 per MW of installed power in the form of community benefits.

Energy-Storage.news’ publisher Solar Media will host the 5th Energy Storage Summit USA, 19-20 March 2024 in Austin, Texas. Featuring a packed programme of panels, presentations and fireside chats from industry leaders focusing on accelerating the market for energy storage across the country. For more information, go to the website.

20 April 2027
Renaissance Dallas at Plano Legacy West Hotel, Dallas, Texas, Dallas
Policy, Procurement and Power Demand: Defining the Next Chapter for Energy Storage. Two days in Dallas where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into US storage, this is that room.

Read Next

October 23, 2026
Tech giant Google and distributed energy resource (DER) platform Voltus have announced an expanded agreement to build a 1GW virtual power plant (VPP) in the US.
October 22, 2026
In recent North American sodium-ion news, Hithium is entering the Canadian market with two BESS solutions, while Peak Energy has closed a Series B financing round led by GM.
October 22, 2026
Science safety leader UL Solutions has announced a new certification pathway intended to help manufacturers of modular direct current (DC) battery energy storage systems (BESS).
October 21, 2026
Distributed energy storage company Viridi and developer and financier Good Carbon Co. have announced the deployment of a 3.75MWh energy storage project in Buffalo, New York.
October 20, 2026
Zinc hybrid cathode battery and storage system maker Eos Energy Enterprises has reported its highest quarterly revenue to date alongside a narrowing gross margin loss.