Fluence and Irish state-owned power group ESB develop next 210MWh of battery storage in portfolio

By Molly Lempriere
October 4, 2021
LinkedIn
Twitter
Reddit
Facebook
Email
Fluence Gridstack BESS at a project site. It’s the 6th generation of technology from the company, which is targeting an IPO. Image: Fluence.

State-owned electricity company ESB and energy storage technology company Fluence have announced two new battery projects in Dublin, Ireland.

The 75MW/150MWh battery in Poolbeg is to be the EU’s largest battery energy storage system (BESS) project by energy capacity, the companies said. A second 30MW/60MWh asset is also to be developed at South Wall, with both batteries to be developed at existing ESB plants.

Together with projects already underway at Inchicore, Dublin, and Aghada, Co Cork, the companies now have a portfolio of 308MWh under development.

The 38MWh Aghada and 60 MWh Inchicore systems are set to come online in early 2022, which the Poolbeg and South Wall batteries are due for completion in early 2023.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“ESB is very excited to be partnering with Fluence in delivering our first battery portfolio of scale onto the Irish grid,” said head of asset development at ESB Generation Trading, Paul Smith.

“This new battery capacity is an example of ESB’s commitment to developing renewables-enabling projects consistent with our Brighter Future Strategy, leading the transition to reliable, affordable low carbon energy. We look forward to working with our partners to safely progress these projects over the coming 18 months.”

The three projects in Dublin, along with the project in Aghada all have a duration of two hours, allowing them to provide grid services that would otherwise be provided by fossil fuel power plants.

The storage sector in Ireland has been heating up, in 2020 its first large-scale battery storage projects were energised, with Statkraft completing its 11MW Kerry battery storage project in January 2020, the first utility-scale battery project in the country. Following this, developer Lumcloon Energy celebrated its 100MW battery storage facility in Co. Offaly being energised in December.

Going forwards, the next year will be key for Ireland’s 70×30 climate ambitions added president for Fluence Europe, Middle East and Africa Paul McCusker.

“Fluence already has a close to 100MWh portfolio of projects with the ESB, and we are delighted to add to that with the Poolbeg and South Wall energy storage solutions. These projects represent a leap forward in terms of reliability for the electricity system and will quickly add much needed flexible capacity in the constrained Dublin area.”

This story first appeared on Solar Power Portal.

Read Energy-Storage.news’ analysis of Fluence’s recent IPO announcement, ‘Fluence IPO ‘can open investment doors for energy storage and renewable energy industry’, here.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

February 23, 2026
European Union countries have made limited progress on energy storage deployment and electricity network flexibility recommendations.
February 20, 2026
A flurry of BESS project news from big-name players in Western Europe in the run-up to the Energy Storage Summit next week, with Neoen, Statkraft, Zenobē and Infranode moving projects forward in Germany, Ireland, the UK and Denmark. Highlights include a 15-year toll between Drax and Zenobē, and multiple 4-hour duration systems.
February 19, 2026
Ukraine’s government sees energy storage as a tool of strategic national importance as the country weathers Russian attacks and looks to the future.
February 18, 2026
More needs to be done to cement energy storage’s vital role in European energy resilience, writes Teresa Casacchia, head of storage at Baywa r.e.
February 12, 2026
A 582MWh battery storage project and a gigawatt-hour-scale thermal energy storage system are the latest big developments in the emerging Baltic region, north-eastern Europe.