Energy Vault and NV Energy commission 440MWh Nevada BESS in ‘compressed schedule’

April 25, 2024
LinkedIn
Twitter
Reddit
Facebook
Email

Energy Vault and utility NV Energy have put a 220MW/440MWh battery energy storage system (BESS) into operation in Nevada, US.

The Reid Gardner BESS project in Moapa, Nevada, was built on the site of a decommissioned coal plant and the 2-hour unit is one of the largest BESS in the state.

The BESS will help NV Energy manage peak demand periods on the grid. The utility, the largest public one in the state, will operate the project which utilises Energy Vault’s BESS hardware and software including its energy management system (EMS) Vault-OS.

Energy Vault described the construction process as a ‘compressed schedule’ while Jimmy Daghlian, VP renewables, NV Energy commented:

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“The overall construction process moved very quickly – which allowed us to bring the project in service for our customers ahead of schedule and ahead of the hot summer months. We appreciate Energy Vault’s problem-solving spirit, commitment, and partnership in bringing this project to life.”

NV Energy was revealed as the owner of the project in December 2022 and construction started in Q2 2023. It is owned by investment firm Berkshire Hathaway, and readers may be familiar with it as one of the main offtakers for the Gemini solar-plus-storage project, one of the world’s largest.

Energy Vault is primarily known for its gravity-based long-duration energy storage (LDES) technology EVx, for which it is close to commissioning its first commercial project in China. The company moved into short-duration with BESS and multi-day LDES with green hydrogen because of a slow take-up of LDES technologies, CEO Rob Piconi explained in an interview last year (Premium access).

24 March 2026
Dallas, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2026!

Read Next

February 10, 2026
Energy storage developer and system integrator Energy Vault and sodium-ion battery energy storage system (BESS) startup Peak Energy have announced a 1.5GWh strategic development agreement.
February 10, 2026
South Korean battery and electronics materials manufacturer Samsung SDI and South Korean state-utility Korea East-West Power (EWP) have signed a memorandum of understanding (MOU) to develop and invest in global energy storage systems (ESS) and renewable energy projects.
Premium
February 9, 2026
Energy-Storage.news Premium speaks to Daniel Dedrick, US-based BESS developer and operator, GridStor’s CTO, about the company’s strategies for navigating FEOC and Section 301 tariffs.
February 9, 2026
Software-focused battery energy storage system (BESS) integrator FlexGen has put two utility-scale BESS projects in operation in Wisconsin and Iowa, US, totalling 700MWh.
February 9, 2026
Chinese battery manufacturer EVE Energy has secured a contract with the Malaysian government to deploy an AC/DC integrated 36MWh solar-plus-storage system at Kuala Lumpur International Airport (KLIA).