Energy Vault and NV Energy commission 440MWh Nevada BESS in ‘compressed schedule’

LinkedIn
Twitter
Reddit
Facebook
Email

Energy Vault and utility NV Energy have put a 220MW/440MWh battery energy storage system (BESS) into operation in Nevada, US.

The Reid Gardner BESS project in Moapa, Nevada, was built on the site of a decommissioned coal plant and the 2-hour unit is one of the largest BESS in the state.

The BESS will help NV Energy manage peak demand periods on the grid. The utility, the largest public one in the state, will operate the project which utilises Energy Vault’s BESS hardware and software including its energy management system (EMS) Vault-OS.

Energy Vault described the construction process as a ‘compressed schedule’ while Jimmy Daghlian, VP renewables, NV Energy commented:

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“The overall construction process moved very quickly – which allowed us to bring the project in service for our customers ahead of schedule and ahead of the hot summer months. We appreciate Energy Vault’s problem-solving spirit, commitment, and partnership in bringing this project to life.”

NV Energy was revealed as the owner of the project in December 2022 and construction started in Q2 2023. It is owned by investment firm Berkshire Hathaway, and readers may be familiar with it as one of the main offtakers for the Gemini solar-plus-storage project, one of the world’s largest.

Energy Vault is primarily known for its gravity-based long-duration energy storage (LDES) technology EVx, for which it is close to commissioning its first commercial project in China. The company moved into short-duration with BESS and multi-day LDES with green hydrogen because of a slow take-up of LDES technologies, CEO Rob Piconi explained in an interview last year (Premium access).

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

June 17, 2026
Developers of battery storage projects across Southeast Asia must heed lessons learned elsewhere and engage with key stakeholders as early as possible, Energy-Storage.news has heard.
June 16, 2026
Energy Dome is advancing a 10-hour CO2 Battery project in Arizona, with SRP and Google, while Invinity announces the sale of North America’s largest VRFB, in California.
June 16, 2026
AESC has announced a strategic supply partnership with BESS system integrator Prevalon Energy.
June 15, 2026
APAC’s AI data centres look set to lock in a decade of coal and gas dependency, but long-duration energy storage can break that cycle, says Pavina Adunratanasee of ArkTerra Partners.
June 12, 2026
Japanese consumer electronics giant Panasonic intends to convert its electric vehicle (EV) battery cell manufacturing facility in Kansas, US, to produce batteries for data centre applications, beginning Q3 of 2029.