Eolian secures US$463 million for 1.7GWh Texas BESS complex

October 14, 2025
LinkedIn
Twitter
Reddit
Facebook
Email

IPP Eolian has closed a US$463 million financing package to support the continued construction of Padua 2 and Padua 3, two battery energy storage systems (BESS) totalling 350MW/1.7GWh in Bexar County, Texas.

This financing, arranged by Natixis Corporate & Investment Banking, enables the completion of the final phases of the Padua Complex, making it, according to Eolian, the largest battery energy storage project in Texas and one of the largest worldwide.

Earlier this month, Eolian and utility CPS Energy began operating Padua 1, the 50MW/100MWh BESS and the first phase of the Padua Complex.

In 2023, CPS signed a storage capacity agreement for Padua 1 with Eolian.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The Padua Complex is expected to be completed in the Spring of 2026, and will provide 400MW/1.8GWh of capacity, sited adjacent to the retiring J.K. Spruce coal plant units and the V.H. Braunig natural gas power plant.

Eolian says the substation location is “critical”, governing south-to-north transmission flows in Texas.

In 2018, the Eolian team identified Padua’s location at a San Antonio transmission hub as a power flow pinch point, which ERCOT also highlighted in 2023 as requiring additional generating resources, including mobile units. 

Construction started earlier this summer on Padua 2, with a capacity of approximately 150MW/750MWh, and Padua 3, with a capacity of approximately 200MW/1,000MWh.

All three projects utilise battery energy storage equipment supplied by Tesla.

Eolian will develop, construct, and operate all three phases of the Padua complex with its in-house asset and optimisation teams.

The US$463 million financing package, arranged by Natixis CIB, covers construction, a term loan, and letter of credit facilities.

By funding Padua 2 and 3 in one closing, Eolian says it guarantees that construction proceeds smoothly, allowing the projects to meet their scheduled operational start dates in Winter and Spring 2026.

H.I.G. Capital-backed energy platform, Greenflash Infrastructure, also recently closed on a hybrid tax capital and debt financing for what it claims to be the largest standalone BESS in Texas, the 400MW/800MWh Project Soho.

Mike Snyder, Vice President of Energy and Charging at Tesla, said of the Padua project:

“The Padua Complex is one of Tesla’s largest global Megapack deployments to date. The 1.8GWh project demonstrates the role batteries play in improving grid utilisation and enabling more efficient operation of all power generation connected to the grid,”

Energy-Storage.news’ publisher Solar Media will host the 12th edition of the Solar & Storage Finance  USA event on 21-22 October 2025 in New York.

Panellists will discuss the fate of US solar and storage in a post-subsidy world, the evolving economics of standalone BESS and de-risking solar and storage supply chains.

Attendees are encouraged to respond to an anonymous survey on the US solar and storage sector, that will shape discussions at the summit. Tickets for the event are available on the official website.

11 November 2025
San Diego, USA
The 2024 Summit included innovative new features including a ‘Crash Course in Battery Asset Management’, Ask-Me-Anything formats and debate-style sessions. You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
24 February 2026
InterContinental London - The O2, London, UK
This isn’t just another summit – it’s our biggest and most exhilarating Summit yet! Picture this: immersive workshop spaces where ideas come to life, dedicated industry working groups igniting innovation, live podcasts sparking lively discussions, hard-hitting keynotes that will leave you inspired, and an abundance of networking opportunities that will take your connections to new heights!

Read Next

October 15, 2025
Energy storage developers are securing significant capital and strategic partnerships, with ESS Inc launching a 50MWh iron flow battery pilot, Energy Vault closing a US$300 million investment, and NineDot obtaining US$175 million in debt financing.
October 15, 2025
The value of developers and optimisers in the BESS lifecycle, thinking about long-term risk and KPIs for maximising the asset have been key themes at the Battery Asset Management Summit UK & Ireland 2025.
Premium
October 15, 2025
The US administration has a clear distaste for climate issues, but economics and data centres can still drive a clean energy transition.
Sponsored
October 15, 2025
At RE+ 2025, the Chinese energy solution provider discusses modular design innovations, efficiency gains, and navigating an uncertain policy landscape.
October 15, 2025
Publicly-owned energy company CleanCo Queensland’s 250MW/500MWh Swanbank battery energy storage system (BESS) has officially registered with AEMO and commenced its testing and commissioning phase.

Most Popular

Email Newsletter