Hydrostor to enter A-CAES project into Ontario LDES procurement

LinkedIn
Twitter
Reddit
Facebook
Email

Long-duration energy storage (LDES) developer-operator Hydrostor intends to enter its compressed air storage project into Ontario, Canada’s recently announced LDES procurement.

Announced 8 May, the Ontario Independent Electricity System Operator (IESO) has launched its Long Lead-Time request for proposal (LLT RFP), aiming to procure up to 800MW of LDES, including pumped hydro.

The LLT RFP is also open to 1TWh of generation resources, and successful projects will be awarded a 40-year contract.

IESO’s LLT RFP builds on its previously announced Long-Term 1 (LT1) and Long-Term 2 (LT2) RFPs.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The LT1 RFP, at the time, resulted in the largest procurement of battery energy storage system (BESS) capacity in the country’s history, awarding over 850MW of BESS capacity contracts across two tranches during May and June of 2023.

LT2 was launched in July 2025, targeting 3TWh of energy generation, alongside 600MW of new capacity resources.

According to the IESO, “the first Window of the Energy Stream of the LT2 RFP has now concluded. The IESO has executed contracts with 13 Selected Proponents, totaling 1,115.10MW of Maximum Contract Capacity and an aggregate Expected Annual Imputed Production of 2.37 TWh. The capacity stream of the LT2 RFP is still currently active, and Proposals are being evaluated.”

Hydrostor’s A-CAES project

On 13 May, Hydrostor announced the development of the Quinte Energy Storage Centre, an advanced compressed air energy storage (A-CAES) project in Greater Napanee, Ontario.

A-CAES technology functions by compressing air into a storage medium during the charging cycle. When electricity is needed, the compressed air is released and heated, causing it to expand and drive a turbine generator.

The company intends to enter the project into the LTT RFP. As reported by Energy-Storage.news Premium in July 2024, Hydrostor previously intended to submit the project to the LT2 RFP.

While the company did not specify project size in its latest announcement, as covered in that ESN Premium article, it was presented with a planned output and capacity of 500MW/8,000MWh to Greater Napanee’s town council, adjacent to Ontario Power Generation’s Lennox Generating Station.

Hydrostor noted that the 13 May announcement followed the project’s receipt of a Municipal Support Resolution from Greater Napanee, the result of a more than 12-month consultation process that allowed the company to engage with the town’s administration, council, and community members to raise awareness and understanding of the project and its benefits.

Now, the Quinte Energy Storage Centre begins the permitting process, during which, Hydrostor said it will continue to work with the Greater Napanee community and provincial and federal agencies, to obtain municipal, provincial, and federal approvals and permits.

The project is also being developed in partnership with the Mohawks of the Bay of Quinte, who will be an Indigenous equity partner in Quinte.

Hydrostor also claimed that Quinte will generate substantial economic value for local and provincial economies. The company estimates thousands of jobs will be supported during construction, with approximately 40 permanent positions maintained throughout the facility’s anticipated 50-year operational period. The total economic impact is expected to exceed CA$1.4 billion (US$1.02 billion) in contributions to Canada’s GDP.

The project will be funded in part by a previously announced investment from the Canada Growth Fund, who have made available a US$50 million convertible development expenditure loan facility to fund a portion of development costs for Hydrostor’s Canadian projects.

In January 2026 Hydrostor announced a strategic technology and equity agreement to incorporate energy infrastructure equipment manufacturer Baker Hughes’ technology into its main design for its A-CAES solution. This included orders for up to 1.4GW of Baker Hughes equipment for Hydrostor’s flagship projects, including compression, expander, motor, and generator technology.

6 October 2026
Warsaw, Poland
The Energy Storage Summit Central Eastern Europe is set to return in September 2025 for its third edition, focusing on regional markets and the unique opportunities they present. This event will bring together key stakeholders from across the region to explore the latest trends in energy storage, with a focus on the increasing integration of energy storage into regional grids, evolving government policies, and the growing need for energy security.

Read Next

May 15, 2026
Spanish developer and independent power producer (IPP) Zelestra has energised its 1GWh battery energy storage system (BESS) in the Atacama Desert in Chile.
May 15, 2026
Nickel-hydrogen battery company EnerVenue has announced a pilot battery energy storage system (BESS) project in Jintan, Changzhou, China.
May 15, 2026
Australia’s New South Wales has seen 532MW of firming projects contracted through its seventh infrastructure tender, securing two projects designed to strengthen electricity supply during periods of peak demand and system stress in the Sydney-Newcastle-Wollongong region.
Premium
May 14, 2026
Energy-Storage.news Premium speaks with Pat Wood III, co-chair at Pew Charitable Trusts about the company’s DER Policy Playbook
May 13, 2026
In this US news roundup, battery energy storage system (BESS) project updates from Spearmint Energy in Texas, Polaris Renewable Energy in Puerto Rico, and Clearway Energy Group in Utah.