Tesla install to bring Europe’s largest community battery to Nottingham

LinkedIn
Twitter
Reddit
Facebook
Email
Representatives of the energy consortium behind Trent Basin gather to mark the launch of the pilot scheme. Image: Blueprint

What is expected to be Europe’s largest community battery is set to be installed at an innovative regeneration scheme in Nottingham, England, with a 2MWh Tesla battery to be deployed in September as part of a housing scheme alongside community solar.

The £100 million (US$129.7 million) Trent Basin project is a new housing development built at the site of an inland dock previously derelict for around two decades. It is expected to deliver 500 homes over five phases with 375kW of rooftop and ground mounted solar and the Tesla battery to be installed by EvoEnergy.

In an innovative use of the solar farm, planning permission has been granted on the basis that the site shall be cleared by 28 February 2020. By this time, the panels from the ground mounted installation will be removed and installed on new homes built as part of the development.

With the addition of the battery storage facility and ground source heat pumps which will also be used on site, Trent Basin is intended to provide a new way to use renewable energy sources by generating, storing and distributing all at a neighbourhood level. A local energy company, Trent Basin ESCO, has already been set up to facilitate the local energy services.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

According to project lead Blueprint, the battery will store energy from the local renewable generation to be used on site while also performing grid arbitrage and smoothing out the peaks and troughs of supply and demand.

UK energy: ‘inefficient and carbon intensive’

“The way we generate and distribute energy in the UK is inefficient and carbon intensive. It doesn’t have to be like this. With new technologies, especially in renewable energy and storage it is possible to do better,” commented Blueprint’s chief executive Nick Ebbs.

The pilot is intended to demonstrate how to lower cost and reduce carbon whilst allowing residents to better engage with the energy they consume. Residents that opt into the scheme will have photovoltaic panels installed on their roofs, and be provided with smart meters and voice controlled speakers for access to live data on energy created, stored and consumed.

It is expected to provide energy savings of around 30% compared to conventional house developments and has already attracted several homeowners who have either bought or reserved properties.

Councillor Alan Clark, portfolio holder for energy and sustainability at Nottingham City Council, said: “I am delighted that Nottingham has been chosen to pilot this innovative scheme. This highlights that the city is at the cutting edge of energy innovation, having the right people and infrastructure to get these types of projects off the ground. This growth in community renewable energy will help to sustain our status as the most energy self-sufficient city in the UK.”

Trent Basin is being supported by £6 million of grant funding from two energy programmes run by Innovate UK, while a consortium has come together to deliver the scheme, including business, government and academia and led by public private partnership Blueprint.

Ebbs added: “Technologies now exist that mean we can deliver community energy in a way that can bring real benefits to consumers and significantly reduce carbon. The barrier to adoption has been the complexity of putting consumers, new technologies and business models together in a way that makes it all work. That is why Innovate UK is supporting this pilot. We feel privileged to be involved in such a ground-breaking initiative.”

Read Next

September 3, 2025
During the morning of 30 August 2025, the California Department of Forestry and Fire Protection (CAL FIRE) responded to a possible vegetation fire in the area of independent power producer (IPP) Arevon Energy’s California Flats solar-plus-storage project.
Premium
September 3, 2025
The UK had one of its best months of the year for large-scale BESS projects being completed in August.
September 2, 2025
Energy-Storage.news speaks with Karina Hershberg, Associate Principal at engineering firm PAE Engineers, on integrating microgrids with sustainable building design.
September 2, 2025
The sale of the UK BESS-holding Harmony Energy Income Trust (HEIT) proved private capital’s greater patience and valuation around the asset class, the CEO of its former investment advisor told Energy-Storage.news.
September 2, 2025
The market share of vertically integrated battery cell and BESS companies has fallen since 2023, market intelligence firm Rho Motion said.

Most Popular

Email Newsletter