Terra-Gen to investigate cause of Valley Center California BESS fire with ‘incident over’

LinkedIn
Twitter
Reddit
Facebook
Email

Developer Terra-Gen will now investigate the cause of a fire at its Valley Center BESS in California, with public safety measures lifted and the incident considered “over”.

A battery storage unit in the Valley Center Energy Storage System caught fire at approximately 5.15 pm local time yesterday (18 September), Terra-Gen said in media statement provided to Energy-Storage.news.

Fire and Sheriff’s departments were dispatched, roads were closed and an evacuation order for the surrounding 1/4 mile was issued, while a shelter in place for the 1/2 mile around the site was also issued, however these were only kept in place for at most four hours.

The facility’s design kept the incident contained and the measures were lifted by 9.15 pm the same evening, Terra-Gen said in a statement at 5.05 am local time (Pacific Daylight Time) today (19 September).

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

San Diego County Hazardous Materials team monitored the air and water around the site during the incident and found no hazardous conditions, the statement added, finishing:

“Now that the incident is over, Terra-Gen will investigate the cause of the fire with the support of
the Valley Center Fire Department.”

The project, near San Diego, was announced as online by Terra-Gen in March 2022 and has an energy storage capacity of 140MW/560MWh.

It made headlines earlier this year when some 100 LG lithium-ion battery packs were stolen from late December 2022 through January 2023. Energy-Storage.news was told by Terra-Gen in March, a few weeks after the incident, that these were decommissioned, palletised and awaiting transportation to a recycling centre.

Asked why these were decommissioned, the spokesperson a week later said that a “a sensor system fault triggered the water-based protection systems resulting in the batteries in question to be taken out of service”.

Faulty sprinkler systems have also been described as the cause of several other notable fires at large-scale battery storage projects, including Moss Landing Energy Storage Facility, also in California.

Read Next

October 5, 2026
Statkraft and Greenvolt Power have signed a 10-year tolling agreement covering 400MW of BESS across two operating projects in Poland.
October 2, 2026
Outgoing California Governor Gavin Newsom recenty addressed approximately 1,200 bills, including several energy storage and solar related bills that were either approved or vetoed.
October 2, 2026
Welcome to another edition of hot takes, snap analysis, gossip and of course, valuable insights from the LinkedIn feeds of energy storage and electricity insiders.
October 2, 2026
Fu-Gen has sold a 100MW ready-to-build battery storage project in Finland to Nala Renewables, extending their Nordic BESS pipeline to 275MW.
October 2, 2026
NSW’s IPC has approved BayWa r.e.’s Bullawah Wind Farm, pairing 804MW of wind with a 718MWh battery in the South West REZ.