Developer Spearmint Energy is nearing the completion of its first project, a 150MW/300MWh battery storage system in Texas using Sungrow battery energy storage system (BESS) equipment.

Spearmint Energy said this morning that commissioning has begun at the project, called Revolution, which will participate in Texas’ ERCOT power market.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

Revolution uses Sungrow’s PowerTitan Series liquid-cooled BESS solution, with lithium iron phosphate (LFP) chemistry batteries. Sister site PV Tech ran a webinar with the Chinese PV inverter and energy storage manufacturer and integrator a few months ago, launching the PowerTitan product, which you can watch here.

Startup Spearmint was only founded in 2021, and has three strategic areas of focus: solar PV and battery storage project development, energy storage offtake and power trading of renewable energy.

CEO and founder Andrew Waranch wrote a Guest Blog for this site in July 2022, advocating for the use of battery storage in Texas to help the state integrate higher shares of variable renewable energy (VRE) from wind and solar onto the “broken” ERCOT grid, while maintaining reliability and security of supply.

Just a few days after that blog was published, Spearmint announced its acquisition of the Revolution project from Con Edison Development. Revolution is located next to a 279MW wind farm in Texas’ Upton County.   

The timeline of development kept pace, and in December 2022, Spearmint Energy broke ground on the project, hiring engineering, procurement and construction (EPC) contractor Mortenson to work on it.

A few months after that, in March this year, Spearmint made further Texas acquisitions, buying three projects in ERCOT totalling 900MW from an undisclosed developer and operator of clean energy projects that Spearmint said was among the largest in the US.

ERCOT projected to reach 8GW, overtaking CAISO

Texas, and specifically the ERCOT grid and wholesale market which serves about 80% of the state, has become the fastest-growing utility-scale BESS market in the US by state or transmission grid in recent years, overtaking California.  

According to S&P Global, 70% of the 710MW total of new BESS deployed in the US in the first quarter of 2023, for example, was in ERCOT. Meanwhile, from an installed base of around 2GW as of the end of Q1, the market is expected to grow to 8GW by the end of 2023. California recently just passed the 5GW mark on its main CAISO grid.

This growth has led to discussion over when market saturation might be reached. Meanwhile, Spearmint Energy got involved in a high profile discussion over the merits of artificial intelligence (AI)-driven trading of energy from battery storage systems through the pages of this site.

A Spearmint Energy representative had said the company was sceptical of the value of so-called ‘black box’ optimisation, prompting David Miller, VP of business development at Gridmatic, one such optimiser, to offer the rebuttal that the financial results should speak for themselves.

Prudence Heck and Andrew Young of Spearmint Energy’s analytics and development team wrote a Guest Blog published on this site yesterday, debating the leveraging of AI and machine learning versus the need for human intervention in the optimisation of BESS market participation.

This article has been amended to reflect that Andrew Waranch is founder of Spearmint Energy and not a co-founder, as was originally stated.

Read Next

Premium
March 1, 2024
Italy grid-scale energy storage market opportunities unlike anywhere else, but many challenges and uncertainties around the different revenue streams remain, including the upcoming MACSE capacity market auction.
February 28, 2024
Sungrow tells Energy-Storage.news that it does not currently have plans to launch its own lithium-ion battery cell production for battery energy storage system (BESS) products, a route being taken by other China-based system integrators. 
Premium
February 26, 2024
BESS route-to-market (RTM) and optimisation firms in the UK are increasingly looking at a wider variety of contracting mechanisms beyond the revenue-share or ‘merchant’ model, developer-operator Eku Energy told Energy-Storage.news.
February 22, 2024
Trina Storage, the energy storage arm of major solar PV company Trina Solar, launched its new battery storage solution Elementa 2, to the global market at this year’s Energy Storage Summit EU.
Premium
February 22, 2024
We caught up with James Li, European energy storage director of inverter and BESS provider Sungrow, at the Energy Storage Summit EU 2024.

Most Popular

Email Newsletter