New York’s biggest fossil fuel plant to become renewables & energy storage hub

July 13, 2022
LinkedIn
Twitter
Reddit
Facebook
Email

Energy asset developer Rise Light & Power will redevelop its 2,480MW Ravenswood Generating Station – New York City’s biggest power plant – as a new renewable energy hub including on-site energy storage.

The 27-acre site in Queens will be turned into a hub integrating various clean energy sources, although the press release is not clear on when the fossil fuel units will be retired nor exactly what renewable capacity will be built on-site.

It does make clear that large-scale battery energy storage will be deployed directly on the facility site, which currently powers 20% of New York City’s needs.

The redevelopment will repurpose existing infrastructure to connect thousands of megawatts of offshore wind and onshore wind, solar, and other clean energy resources from Upstate New York to the City’s grid, a press release said. Ravenswood’s river water intake system will also be repurposed to provide zero-emission thermal energy to nearby communities.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The redevelopment is being carried out under a project Rise Light & Power, owned by energy-focused investor LS Power, is calling ‘Renewable Ravenswood’. It will advance the city’s efforts efforts to accelerate the retirement of the state’s fossil fuel facilities by 2030, the press release said, potentially giving some idea of the timeframe. The project still needs to be approved by regulators.

Praising Rise Light & Power for its decision, U.S. Congresswoman Carolyn B. Maloney said: “The residents of my district have suffered through decades of pollution. A Ravenswood running on offshore wind power will solve this issue. I look forward to seeing a Renewable Ravenswood being a monument to Long Island City’s future as a clean energy provider.”

The area around the plant is notorious for its poor air quality with certain districts bearing the grim nickname ‘asthma alley’.

Fossil fuel plants to renewable hubs: a growing trend

Large, legacy power plants provide great locations for storage-enabled renewable hubs thanks to their existing grid connection infrastructure, a lack thereof being one of the largest impediments to getting greenfield projects off the ground.

New York in particular is the subject of much discussion around this, with a large quantity of peaker plants and many in close proximity to urban residents as highlighted before by commentators on the Ravenswood redevelopment. A study last year found that renewable energy, energy efficiency and energy storage can be used to effectively retire New York City’s 6GW of peaker plants by 2030.

A few weeks ago, Energy-Storage.news reported on private equity investment firm ArcLight announcing that its portfolio of legacy power plants are now viewed as excellent locations for battery projects.

It has a total portfolio of nearly 5GW of plants across California, Connecticut and New York State and has already made public plans to install 350MWh of batteries across two plants run by owned affiliate Generation Bridge and 485MWh across three run by another, Eastern Generation.

24 March 2026
Dallas, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2026!

Read Next

December 16, 2025
In this edition of the Energy-Storage.news US news roundup, EticaAG partners with Shell on battery immersion tech, Pacific Northwest National Laboratory begins utility-scale battery testing, and ON.Energy announces a transformer supply agreement.
December 16, 2025
 Utility Georgia Power has reached an agreement with the Public Interest Advocacy (PIA) staff of the Georgia Public Service Commission (PSC), that, if approved, will help lower energy costs and meet electricity demand in the state.
Premium
December 16, 2025
Calibrant’s BESS for a new data centre in Oregon, US, was hailed as the first of its kind, but what are the details beyond the headline? We caught up with Calibrant’s CCO to discuss the practical, commercial and technical specifics of the project.
December 16, 2025
Waratah Super Battery developer Akaysha Energy has put the first phase of its Ulinda Park BESS project into operation in Queensland, Australia.
December 15, 2025
Trade association Energy Storage Europe (ESE) has welcomed proposed reforms to European Union (EU) grid connection and permitting processes.