Plus Power signs ESA for 800MWh Alabama BESS

LinkedIn
Twitter
Reddit
Facebook
Email

Developer-operator Plus Power and utility Tennessee Valley Authority (TVA) announced a 20-year energy storage agreement (ESA) for the 200MW/800MWh Crawfish Creek battery energy storage system (BESS) in Alabama, US.

Announced 21 April, TVA, the largest public energy provider in the US, selected the project through a request for proposal (RFP) issued in early 2025 to supply new capacity resources across the region. 

Speaking with Energy-Storage.news about the project, Brian Duncan, Plus Power’s chief commercial officer said that TVA “has growing energy demand in the Southeast, so battery storage is deeply needed for its ability to rapidly deploy and rapidly respond to TVA’s needs.”

Duncan continued, “The Chattanooga-Huntsville corridor is growing due to industrialisation, military, and aerospace innovation, so this facility is perfectly sited to help meet those needs.”

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Duncan also said the BESS, located in Jackson County, Alabama, “will serve TVA’s operational needs and respond to its dispatch instructions.” It is not a merchant trading opportunity.

Under the agreement, TVA will charge and dispatch energy from Crawfish Creek based on system needs, while Plus Power’s Crawfish Creek Energy Storage retains ownership of the facility. 

Crawfish Creek will also provide grid-forming capabilities, fast frequency response, regulation, and operating reserves, to help support growth in manufacturing, data centres, and industrial investment across the Tennessee Valley. 

Construction on the project is expected to begin in 2028, with commercial operation anticipated in summer 2029. Plus Power claimed the project is expected to create 50 to 100 construction jobs in Jackson County and support four full-time operations roles once completed. 

Plus Power also stated that Crawfish Creek contributes to TVA’s larger initiative to bring 6,200MW of additional generation capacity online in response to rising electricity demand throughout north Alabama and the Tennessee Valley region.

Over the last five years, TVA reports that its economic development initiatives have facilitated the creation of more than 91,000 new jobs, preserved 235,000 existing positions, and generated US$45.9 billion in anticipated capital investment across Alabama.

The news of the Crawfish Creek ESA came shortly after TVA and IPP Tenaska, through its affiliate Bobwhite Energy Storage, announced a long-term ESA for the 225MW/900MWh Bobwhite BESS project in East Tennessee.

Alabama and Plus Power

According to the US Energy Information Administration (EIA), approximately 9% of Alabama’s total electricity was generated by renewables in 2024. Of that 9%, hydroelectric facilities made up about 65% of renewables generation.

Approximately 25% came from biomass, mainly wood and wood-derived fuels, and 10% was generated by solar.

EIA also explains that Alabama’s strongest solar potential is concentrated in the state’s southeastern corner and along its brief Gulf Coast coastline.

The state’s inaugural utility-scale solar facility, a 30MW PV installation, commenced operations in late 2015 on the Alabama side of the Fort Benning US Army base. In late 2021, a 227MW solar farm in northwest Alabama became operational, representing the state’s largest solar project and providing electricity to a major data center.

Earlier this year, the US Department of Energy (DOE) closed a US$26.5 billion loan package with two wholly owned subsidiaries of utility Southern Company, in Georgia and Alabama.

In Southern Company’s Alabama-based subsidiary, Alabama Power’s 2025 integrated resource plan (IRP), the company considers traditional BESS and medium-duration energy storage systems (MDESS) with approximately 12 hours of duration.

The utility revealed Alabama’s first utility-scale battery storage project in March 2025, a 150MW system in Walker County that will occupy the former site of the Gorgas coal plant, which ceased operations in 2019.

A year earlier, EPRI, Southern Company, and Storworks wrapped up testing on a concrete thermal energy storage pilot project that was described as the world’s largest demonstration of the technology at that time.

In January, Southern Company announced plans to deploy technology from US-based iron-sodium battery manufacturer Inlyte Energy at its Energy Storage Test Site in Wilsonville, Alabama. The demonstration project is sized at 80kW/1.5MWh.

Plus Power stated that with Crawfish Creek, the company is entering its seventh state market and expanding into the Southeast. The company said that it currently owns and operates nine facilities in Arizona, Hawaii, Maine, Massachusetts, and Texas, totaling 1,650 MW/4,150MWh. 

In February, Plus Power announced it had begun operating the 175MW/350MWh Cross Town BESS in Gorham, Maine, which according to the company, is the largest BESS of its kind on the ISO New England grid.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.
26 November 2026
9am GMT / 1pm GST
In this webinar, Florian Didier and Salomé Perperot from Clean Horizon share the approach they use when supporting IPPs through optimiser selection and contract negotiation across Europe. The presentation will be followed by a live Q&A session in which attendees can put their own questions to the speakers. Who should attend: IPPs and developers, asset owners and investors, lenders and financial advisors, and anyone involved in the commercial structuring of battery storage projects.
22 February 2027
InterContinental London - The O2, London, UK
The Future of Energy Storage Starts Here Three days in London where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into European storage, this is that room.
20 April 2027
Renaissance Dallas at Plano Legacy West Hotel, Dallas, Texas, Dallas
Policy, Procurement and Power Demand: Defining the Next Chapter for Energy Storage. Two days in Dallas where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into US storage, this is that room.

Read Next

Premium
October 30, 2026
Few grids illustrate the strain of America’s data centre boom more starkly than the PJM Interconnection.
October 30, 2026
Demand for 8-hour battery energy storage in Australia is “completely artificial” and relies on government underwriting, according to Tesla, which said asymmetric registration can help such projects earn more.
October 30, 2026
Germany-headquartered inverter manufacturer SMA has launched a grid-forming solar-plus-storage solution in Australia, unveiling it at the All-Energy Australia 2026 event in Melbourne this week.
October 29, 2026
The California Energy Commission (CEC) has released over US$46 million for the state’s Distributed Electricity Backup Assets (DEBA) Programme.
October 29, 2026
Distributed energy resource (DER)-focused company FranklinWH has recently announced advancements in residential energy storage programmes in Louisiana and Iowa.