Plus Power closes US$219m financing for Hawaii’s biggest battery project so far

Share on linkedin
LinkedIn
Share on twitter
Twitter
Share on reddit
Reddit
Share on facebook
Facebook
Share on email
Email
Rendering of how the 185 MW / 565 MWh Kapolei Energy Storage project will look. Image: Plus Power

US$219 million of financing has been secured by developer Plus Power for the 185MW / 565MWh Kapolei Energy Storage (KES) project in O’ahu, Hawaii. 

Plus Power said earlier this week that it had closed the credit facility comprising US$188 million in non-recourse construction debt and US$31 million in letters of credit, through financing led by Mizuho Securities USA and KeyBank. 

Silicon Valley Bank and CoBank also joined in the facility for the standalone battery energy storage system (BESS) project, on which construction began in August. It is scheduled to go into operation during 2022.  

A power purchase agreement (PPA) was signed for KES with utility Hawaiian Electric in late 2020. The facility will enable the retirement of Hawaii’s last remaining coal power plant, the 180MW AES Hawaii Power Plant. 

Plus Power’s contract award was made following a competitive solicitation round in which Hawaiian Electric also handed contracts to 15 other projects, including solar-plus-storage and standalone energy storage

Kapolei Energy Storage is the largest energy storage project selected by the utility in a procurement round to date. It will provide capacity and allow the utility to store energy generated at off-peak times and times of abundant renewable energy generation, shifting it to be used when demand peaks.

The BESS will also be used to deliver 50MW of fast frequency response services to the local grid and support Hawaiian Electric by providing virtual inertia and blackstart capabilities to maintain grid stability and enable offline power plants and other infrastructure to be brought back online quickly. 

There had been some challenges in the project’s development, as although the regulatory Hawaiian Public Utilities Commission (PUC) had approved the September 2020 PPA, it retained some concerns that the batteries could be charged using fossil fuel energy with the project set to come online before sufficient renewable capacity buildout. 

However after negotiations, an agreement was reached and PUC gave its approval. 

“This landmark financing highlights Plus Power’s ability to execute on projects that deliver energy, capacity and grid services for our customers and attract capital from top tier financiers like Mizuho and KeyBank,” Plus Power’s general manager Brandon Keefe said. 

Plus Power focuses on standalone battery storage project development and has other large-scale projects in development around the US including proposed facilities in Maine (175MW / 350MWh), Massachusetts (150MW / 300MWh) and Georgia (150MW / 600MWh) that it hopes it can bring online by the end of 2024. 

“Very rapid growth in standalone battery storage projects will be needed to transition the grid to 100% renewable energy,” Keefe said.

“Should standalone energy storage become eligible for the federal production tax credit, matching access by hybrid energy storage, we will be able to expedite gigawatts of Plus Power projects to support wholesale markets.”

The success Plus Power is having so far is in contrast to the recent abandonment by ENGIE North America of a solar-plus-storage project on Hawaii Island that it was awarded a contract for by Hawaiian Electric in the same procurement round. 

ENGIE North America cited elevated interconnection costs, as well as issues with supply chain, production and tariffs and trade disputes that are affecting the global solar PV industry as reasons for ditching the project and 25-year PPA

Meanwhile, Hawaiian Electric said in a draft Request for Proposals (RfP) for a renewable energy procurement for Hawaii Island that it wants all solar PV project bids in the forthcoming round to include energy storage

Read Next

August 8, 2022
Vistra Energy will have more than 1,213MW of battery storage in operation in its portfolio by 2026, the US power generation company has claimed.
August 8, 2022
Global battery energy storage system (BESS) integrator Fluence is setting up a new contract manufacturing facility in Utah to serve the US market.
August 8, 2022
The Inflation Reduction Act took a significant step forward over the weekend as US vice-president Kamala Harris cast a decisive vote.
August 5, 2022
The Department of Planning and Environment in New South Wales gave development approval to a proposed 500MW/1,000MWh battery storage project.
August 4, 2022
Neoen saw its energy storage revenues triple in the first half of this year, driven by its Victorian Big Battery in Australia.

Most Popular

Email Newsletter