One battery fire is ‘a fire for everyone in the industry’ – Energy Storage Summit USA 2024

March 19, 2024
LinkedIn
Twitter
Reddit
Facebook
Email

Battery storage developers and operators discussed the challenges and opportunities in the US market, on the first day of Solar Media’s Energy Storage Summit (ESS) USA 2024.

The two-day event kicked off today in Austin, Texas, and brings together energy storage industry stakeholders operating across the US. Speakers in the opening panel discussion – Prospecting New Market Opportunities – touched on new opportunities, project development and, of course, fire safety.

“One fire for one battery is a fire for everyone in the industry,” said Aron Branam, VP development and construction for developer and independent power producer (IPP) Arevon Energy. Mike DeSocio, founder & CEO of developer Luminary Energy, agreed, saying “…there has been a lot of trust lost in batteries in New York in the last few years”.

All agreed a lot of work needed to be done to assuage those concerns as well as making local communities and decision-makers more familiar with energy storage. Tao Kong, managing partner of developer Luminous Energy said that, despite this, developing batteries is nonetheless easier than developing solar or wind ‘at the moment’.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

He said three key considerations for the market were finding interconnection points, the buildout of the state’s transmission network and economic development in specific areas. It has fewer environmental concerns, a smaller footprint and zoning decisions often class it as ‘industrial’ rather than ‘renewable overlay’ which can be easier to develop.

Prior to that discussion, DeSocio had discussed how to capitalise on opportunities in the New York state market. “You’ll see much more front-of-meter (FTM) storage coming in New York (NY) State in the next few years,” he said.

Finding partners with existing connections is key, and that can include legacy generation, with grid operator NYISO putting in work to make it easy to combine fossil fuel and energy storage. A lot of transmission infrastructure is being built too and this can affect the business case for a specific location, by reducing congestion, for example.

Economic development in specific areas like northern New York is also creating opportunities, particularly for partnering with new economic or manufacturing hubs for an energy storage resiliency play, with two-week outages not unheard of in some parts.

On the Southwest US, developer Avantus’ senior director energy markets Gigio Sakota said that a shortage of Resource Adequacy (RA) capacity in the region is coming, after historically having an excess, a lot of which was exported to demand hub California.

“Storage can help replace that capacity,” Sakota said.

Energy-Storage.news’ publisher Solar Media is hosting the 6th Energy Storage Summit USA, today and tomorrow (19-20 March 2024) in Austin, Texas. It features a packed programme of panels, presentations and fireside chats from industry leaders focusing on accelerating the market for energy storage across the country. For more information, go to the website.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

April 15, 2026
Industry leaders warned that “unfettered optimism” regarding battery degradation is hitting a wall of operational reality.
April 15, 2026
Developer Rye Development are partnering with Kentucky, US utility companies Louisville Gas and Electric (LG&E) and Kentucky Utilities (KU), on a 266MW/2,128MWh pumped hydro energy storage (PHES) project.
April 15, 2026
Thermal management means cost, complexity and aux power consumption for battery storage projects, writes William Lauwers of Enertis Applus+.
April 14, 2026
Informa Markets is launching the inaugural Battery Asset Management Summit, Canada (BAM Canada).
April 14, 2026
A panel at the 2026 US Energy Storage Summit in Dallas, Texas, focused on the evolving landscape of battery energy storage system (BESS) procurement.