One battery fire is ‘a fire for everyone in the industry’ – Energy Storage Summit USA 2024

March 19, 2024
LinkedIn
Twitter
Reddit
Facebook
Email

Battery storage developers and operators discussed the challenges and opportunities in the US market, on the first day of Solar Media’s Energy Storage Summit (ESS) USA 2024.

The two-day event kicked off today in Austin, Texas, and brings together energy storage industry stakeholders operating across the US. Speakers in the opening panel discussion – Prospecting New Market Opportunities – touched on new opportunities, project development and, of course, fire safety.

“One fire for one battery is a fire for everyone in the industry,” said Aron Branam, VP development and construction for developer and independent power producer (IPP) Arevon Energy. Mike DeSocio, founder & CEO of developer Luminary Energy, agreed, saying “…there has been a lot of trust lost in batteries in New York in the last few years”.

All agreed a lot of work needed to be done to assuage those concerns as well as making local communities and decision-makers more familiar with energy storage. Tao Kong, managing partner of developer Luminous Energy said that, despite this, developing batteries is nonetheless easier than developing solar or wind ‘at the moment’.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

He said three key considerations for the market were finding interconnection points, the buildout of the state’s transmission network and economic development in specific areas. It has fewer environmental concerns, a smaller footprint and zoning decisions often class it as ‘industrial’ rather than ‘renewable overlay’ which can be easier to develop.

Prior to that discussion, DeSocio had discussed how to capitalise on opportunities in the New York state market. “You’ll see much more front-of-meter (FTM) storage coming in New York (NY) State in the next few years,” he said.

Finding partners with existing connections is key, and that can include legacy generation, with grid operator NYISO putting in work to make it easy to combine fossil fuel and energy storage. A lot of transmission infrastructure is being built too and this can affect the business case for a specific location, by reducing congestion, for example.

Economic development in specific areas like northern New York is also creating opportunities, particularly for partnering with new economic or manufacturing hubs for an energy storage resiliency play, with two-week outages not unheard of in some parts.

On the Southwest US, developer Avantus’ senior director energy markets Gigio Sakota said that a shortage of Resource Adequacy (RA) capacity in the region is coming, after historically having an excess, a lot of which was exported to demand hub California.

“Storage can help replace that capacity,” Sakota said.

Energy-Storage.news’ publisher Solar Media is hosting the 6th Energy Storage Summit USA, today and tomorrow (19-20 March 2024) in Austin, Texas. It features a packed programme of panels, presentations and fireside chats from industry leaders focusing on accelerating the market for energy storage across the country. For more information, go to the website.

24 March 2026
Dallas, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2026!

Read Next

Premium
January 14, 2026
Energy-Storage.news Premium speaks with Phil Tonkin, field chief technology officer at Dragos, and Dr. Peter Fox-Penner, a Brattle principal, on BESS cybersecurity.
January 14, 2026
Data centre developer CyrusOne and independent power producer (IPP) Eolian have announced the deployment of a 200MW data centre campus at a pre-existing grid-scale battery energy storage system (BESS) site in Fort Worth, Texas, US.
January 13, 2026
The Governor of Illinois, JB Pritzker, has signed a clean energy bill into law that will boost solar PV and energy storage investments in the state, among others.
January 9, 2026
Jointly owned by Masdar and Igneo Infrastructure Partners, independent power producer (IPP) Terra-Gen’s Lockhart CL I and II battery energy storage system (BESS) projects have reached commercial operations in San Bernardino County, California, US.
January 9, 2026
2025 saw genuinely large-scale BESS projects start construction in Germany, strengthening confidence among stakeholders. But significant challenges remain around grid connection, connection agreements and access to revenue streams, an operator said.